17-00637-00-GR
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | William Charles Construction Company, LLC Low bidder | $1,012,075 | ||
| 2 | Martin & Company Excavating | $1,418,863 | +40.2% | |
| 3 | Curran Contracting Company | $1,444,444 | +42.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 William Charles… | #2 Martin & Compan… | #3 Curran Contract… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0327584 | GRAD& SHAP SHLDRS SPL | 5,900 | FOOT | $15.96 | $31.00 | $35.00 | |
| 2 | X6330725 | SPBGR (SHORT RADIUS) | 162.5 | FOOT | $34.75 | $52.00 | $40.00 | |
| 3 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $62,340.95 | $21,100.00 | $30,000.00 | |
| 4 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $5,000.00 | $14,400.00 | $5,000.00 | |
| 5 | 35101400 | AGG BASE CSE B | 3,600 | TON | $25.59 | $41.00 | $80.00 | |
| 6 | 48203029 | HMA SHOULDERS 8 | 4,800 | SQ YD | $57.29 | $76.00 | $55.00 | |
| 7 | 50104000 | BRIDGE RAIL REMOVAL | 225 | FOOT | $43.16 | $131.00 | $150.00 | |
| 8 | 60600605 | CONC CURB TB | 64 | FOOT | $100.00 | $102.00 | $200.00 | |
| 9 | 63000001 | SPBGR TY A 6FT POSTS | 3,525 | FOOT | $26.83 | $40.80 | $35.00 | |
| 10 | 63000030 | SPGR ATT TO CULVERT | 775 | FOOT | $187.99 | $250.00 | $240.00 | |
| 11 | 63100041 | TRAF BAR TERM T1B | 1 | EACH | $1,859.95 | $2,550.00 | $2,067.67 | |
| 12 | 63100089 | TRAF BAR TERM T6B | 8 | EACH | $3,279.91 | $4,550.00 | $4,000.00 | |
| 13 | 63100167 | TR BAR TRM T1 SPL TAN | 39 | EACH | $2,689.93 | $3,660.00 | $3,500.00 | |
| 14 | 63200310 | GUARDRAIL REMOV | 3,362.5 | FOOT | $5.40 | $12.00 | $8.00 | |
| 15 | 67100100 | MOBILIZATION | 1 | L SUM | $70,264.17 | $84,000.00 | $91,051.77 |