D9 PATCH 2023-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $538,851 | ||
| 2 | G. M. Sipes Construction, Inc. | $555,600 | +3.1% | |
| 3 | Kinney Contractors, Inc. | $637,192 | +18.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 G. M. Sipes Con… | #3 Kinney Contract… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7010520 | TC-PROT 701201 SPL | 1 | L SUM | $43,240.49 | $27,000.00 | $30,000.00 | |
| 2 | 42000060 | WELDED WIRE REINF | 673 | SQ YD | $15.22 | $10.00 | $17.00 | |
| 3 | 44201025 | CL B PATCH T4 14 | 673 | SQ YD | $194.09 | $230.00 | $225.00 | |
| 4 | 44201299 | DOWEL BARS 1 1/2 | 426 | EACH | $36.25 | $25.00 | $25.00 | |
| 5 | 44201403 | CL C PATCH T2 14 | 213 | SQ YD | $195.00 | $225.00 | $280.00 | |
| 6 | 44201407 | CL C PATCH T3 14 | 359 | SQ YD | $190.00 | $225.00 | $270.00 | |
| 7 | 44201409 | CL C PATCH T4 14 | 883 | SQ YD | $187.00 | $225.00 | $252.00 | |
| 8 | 44213200 | SAW CUTS | 1,377 | FOOT | $9.89 | $0.0100 | $8.00 | |
| 9 | 44213204 | TIE BARS 3/4 | 102 | EACH | $30.71 | $20.00 | $17.00 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $27,933.96 | $27,000.00 | $25,000.00 | |
| 11 | 70100820 | TRAF CONT-PROT 701451 | 1 | L SUM | $5,747.64 | $0.0100 | $2,000.00 | |
| 12 | 70103815 | TR CONT SURVEILLANCE | 28 | CAL DA | $0.0100 | $0.0100 | $10.00 | |
| 13 | 70107025 | CHANGEABLE MESSAGE SN | 112 | CAL DA | $125.03 | $0.0100 | $130.00 |