D9 PATCH 2022-10
- Let date
- Friday, June 17, 2022
- Contract
- 78955 · job page
- District
- District 9
- County
- Union, Johnson
- Highway
- Limits
- 12.7 miles of patching on the I-57 northbound lanes from mile marker 44 to mile marker 31.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $638,849 | ||
| 2 | Kinney Contractors, Inc. | $693,786 | +8.6% | |
| 3 | G. M. Sipes Construction, Inc. | $758,459 | +18.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Kinney Contract… | #3 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|
| 1 | 44200050 | WELDED WIRE REINF | 143 | SQ YD | $40.07 | $20.00 | $15.00 | |
| 2 | 44201019 | CL B PATCH T2 14 | 1,696 | SQ YD | $193.00 | $255.00 | $295.00 | |
| 3 | 44201023 | CL B PATCH T3 14 | 43 | SQ YD | $180.00 | $253.00 | $295.00 | |
| 4 | 44201025 | CL B PATCH T4 14 | 100 | SQ YD | $175.00 | $251.00 | $295.00 | |
| 5 | 44201299 | DOWEL BARS 1 1/2 | 4,100 | EACH | $21.08 | $25.00 | $20.00 | |
| 6 | 44213200 | SAW CUTS | 10,120 | FOOT | $7.11 | $1.00 | $4.95 | |
| 7 | 44213204 | TIE BARS 3/4 | 21 | EACH | $37.76 | $17.00 | $15.00 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $21,355.22 | $43,000.00 | $35,000.00 | |
| 9 | 70100420 | TRAF CONT-PROT 701411 | 7 | EACH | $0.0100 | $1,200.00 | $0.0100 | |
| 10 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $97,546.44 | $50,500.00 | $45,000.00 | |
| 11 | 70103815 | TR CONT SURVEILLANCE | 30 | CAL DA | $0.0100 | $1.00 | $0.0100 | |
| 12 | 70107025 | CHANGEABLE MESSAGE SN | 56 | CAL DA | $44.20 | $135.00 | $25.00 |