7RS-4
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $1,876,543 | ||
| 2 | E. T. Simonds Construction Company | $2,022,893 | +7.8% | |
| 3 | The Kilian Corporation | $2,339,259 | +24.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… | #3 The Kilian Corp… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0326697 | CENTERLN RUM STRIP 8 | 3,460 | FOOT | $2.50 | $2.73 | $1.65 | |
| 2 | Z0034105 | MATL TRANSFER DEVICE | 6,150 | TON | $1.40 | $4.35 | $5.00 | |
| 3 | 20200600 | EXC & GR EX SHOULDER | 273 | UNIT | $233.00 | $299.94 | $180.00 | |
| 4 | 40600290 | BIT MATLS TACK CT | 32,511 | POUND | $0.0100 | $0.0100 | $1.15 | |
| 5 | 40600370 | LONG JOINT SEALANT | 13,786 | FOOT | $3.25 | $3.17 | $2.75 | |
| 6 | 40600982 | HMA SURF REM BUTT JT | 662 | SQ YD | $7.00 | $9.44 | $19.00 | |
| 7 | 40600990 | TEMPORARY RAMP | 113 | SQ YD | $15.00 | $42.04 | $0.0100 | |
| 8 | 40602970 | HMA BC IL-9.5FG N70 | 2,788 | TON | $105.00 | $101.60 | $110.00 | |
| 9 | 40604052 | HMA SC IL-9.5 C N70 | 3,362 | TON | $100.00 | $93.51 | $108.00 | |
| 10 | 40800050 | INCIDENTAL HMA SURF | 42 | TON | $400.00 | $310.51 | $345.00 | |
| 11 | 44000151 | HMA SURF REM 1/2 | 283 | SQ YD | $5.00 | $6.44 | $3.25 | |
| 12 | 44000155 | HMA SURF REM 1 1/2 | 39,537 | SQ YD | $0.9000 | $1.54 | $1.60 | |
| 13 | 44201377 | CL C PATCH T2 12 | 1,311 | SQ YD | $185.00 | $165.00 | $220.00 | |
| 14 | 44201381 | CL C PATCH T3 12 | 329 | SQ YD | $180.00 | $163.00 | $196.00 | |
| 15 | 44201383 | CL C PATCH T4 12 | 736 | SQ YD | $175.00 | $161.00 | $188.00 | |
| 16 | 44213204 | TIE BARS 3/4 | 249 | EACH | $17.00 | $34.50 | $20.00 | |
| 17 | 48102100 | AGG WEDGE SHLD TYPE B | 302 | TON | $64.00 | $99.34 | $65.00 | |
| 18 | 48203029 | HMA SHOULDERS 8 | 11,850 | SQ YD | $40.00 | $43.34 | $53.00 | |
| 19 | 48203100 | HMA SHOULDERS | 32 | TON | $125.00 | $101.11 | $113.00 | |
| 20 | 64200108 | SHOULDER RUM STRIP 8 | 27,298 | FOOT | $0.3000 | $0.2800 | $0.2700 | |
| 21 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $1,600.00 | $2,000.00 | $2,900.00 | |
| 22 | 67100100 | MOBILIZATION | 1 | L SUM | $76,652.77 | $133,524.77 | $120,810.00 | |
| 23 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $4,000.00 | $28,738.47 | $29,625.00 | |
| 24 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $4,000.00 | $7,724.59 | $31,400.00 | |
| 25 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $4,800.00 | $28,156.50 | $53,850.00 | |
| 26 | 70103815 | TR CONT SURVEILLANCE | 6 | CAL DA | $0.0100 | $0.0100 | $0.0100 | |
| 27 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $100.00 | $40.50 | $95.00 | |
| 28 | 70300100 | SHORT TERM PAVT MKING | 4,136 | FOOT | $1.00 | $1.00 | $0.5500 | |
| 29 | 70300150 | SHRT TRM PAVT MK REM | 1,379 | SQ FT | $2.50 | $0.0100 | $0.0100 | |
| 30 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 30,748 | FOOT | $0.0100 | $0.0100 | $0.0100 | |
| 31 | 78001110 | PAINT PVT MK LINE 4 | 30,748 | FOOT | $0.2000 | $0.1800 | $0.1800 | |
| 32 | 78100100 | RAISED REFL PAVT MKR | 172 | EACH | $44.00 | $43.15 | $41.50 | |
| 33 | 78300200 | RAISED REF PVT MK REM | 172 | EACH | $14.00 | $12.27 | $0.0100 | |
| 34 | 78300201 | PAVMT MRKG REM GRIND | 10,249 | SQ FT | $0.0100 | $0.0100 | $0.0100 |