111SLP-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sierra Bravo Contractors, LLC Low bidder | $713,457 | ||
| 2 | Samron Midwest Contracting, Inc. | $818,855 | +14.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sierra Bravo Co… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | Z0022800 | FENCE REMOVAL | 141 | FOOT | $6.38 | $10.00 | |
| 2 | 20100500 | TREE REMOV ACRES | 0.5 | ACRE | $26,649.21 | $25,000.00 | |
| 3 | 20200100 | EARTH EXCAVATION | 7,095 | CU YD | $16.14 | $19.00 | |
| 4 | 20400800 | FURNISHED EXCAVATION | 13,480 | CU YD | $24.13 | $30.00 | |
| 5 | 20700110 | POROUS GRAN EMBANK | 2,350 | TON | $30.03 | $30.00 | |
| 6 | 25000210 | SEEDING CL 2A | 1.25 | ACRE | $5,300.00 | $3,500.00 | |
| 7 | 25000350 | SEEDING CL 7 | 1.25 | ACRE | $477.00 | $2,900.00 | |
| 8 | 25000400 | NITROGEN FERT NUTR | 113 | POUND | $3.18 | $3.50 | |
| 9 | 25000500 | PHOSPHORUS FERT NUTR | 113 | POUND | $3.18 | $3.50 | |
| 10 | 25000600 | POTASSIUM FERT NUTR | 113 | POUND | $3.18 | $3.50 | |
| 11 | 25000700 | AGR GROUND LIMESTONE | 2.5 | TON | $212.00 | $650.00 | |
| 12 | 25100115 | MULCH METHOD 2 | 2.5 | ACRE | $1,060.00 | $2,800.00 | |
| 13 | 25100630 | EROSION CONTR BLANKET | 1,583 | SQ YD | $4.62 | $2.00 | |
| 14 | 28000250 | TEMP EROS CONTR SEED | 125 | POUND | $5.30 | $0.0100 | |
| 15 | 28000400 | PERIMETER EROS BAR | 709 | FOOT | $7.12 | $3.00 | |
| 16 | 44004250 | PAVED SHLD REMOVAL | 336 | SQ YD | $10.92 | $15.00 | |
| 17 | 48100500 | AGGREGATE SHLDS A 6 | 162 | SQ YD | $32.80 | $30.00 | |
| 18 | 48203029 | HMA SHOULDERS 8 | 60 | SQ YD | $127.41 | $160.00 | |
| 19 | 60100060 | CONC HDWL FOR P DRAIN | 3 | EACH | $669.45 | $950.00 | |
| 20 | 60108100 | PIPE UNDERDRAIN 4 SP | 102 | FOOT | $38.55 | $30.00 | |
| 21 | 60109640 | BACKSLOPE DRAIN T3 4 | 800 | FOOT | $26.06 | $20.00 | |
| 22 | 63000001 | SPBGR TY A 6FT POSTS | 25 | FOOT | $53.00 | $75.00 | |
| 23 | 63100085 | TRAF BAR TERM T6 | 1 | EACH | $6,890.00 | $9,000.00 | |
| 24 | 63100167 | TR BAR TRM T1 SPL TAN | 1 | EACH | $5,830.00 | $6,000.00 | |
| 25 | 63200310 | GUARDRAIL REMOV | 556 | FOOT | $5.30 | $8.00 | |
| 26 | 66700705 | FUR ERECT DRAIN MKRS | 6 | EACH | $408.83 | $450.00 | |
| 27 | 67000400 | ENGR FIELD OFFICE A | 2 | CAL MO | $2,650.00 | $1,500.00 | |
| 28 | 67100100 | MOBILIZATION | 1 | L SUM | $42,728.60 | $49,000.00 | |
| 29 | 70100100 | TRAF CONT-PROT 701316 | 1 | EACH | $14,186.49 | $20,000.00 | |
| 30 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $5,300.00 | $3,500.00 | |
| 31 | 70106500 | TEMP BR TRAF SIGNALS | 1 | EACH | $18,020.00 | $18,000.00 | |
| 32 | 70106700 | TEMP RUMBLE STRIPS | 6 | EACH | $768.50 | $950.00 | |
| 33 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $79.50 | $100.00 | |
| 34 | 70300150 | SHRT TRM PAVT MK REM | 358 | SQ FT | $5.28 | $0.0100 | |
| 35 | 72501000 | TERMINAL MARKER - DA | 1 | EACH | $74.20 | $50.00 | |
| 36 | 78001110 | PAINT PVT MK LINE 4 | 1,242 | FOOT | $3.63 | $2.00 | |
| 37 | 78200005 | GRDRAIL REF TYPE A | 4 | EACH | $10.60 | $3.50 | |
| 38 | 78300201 | PAVMT MRKG REM GRIND | 215 | SQ FT | $12.21 | $10.00 |