D9 CM PAVT JOINT REPAIR 2020-1
- Let date
- Friday, March 6, 2020
- Contract
- 78766 · job page
- District
- District 9
- County
- Williamson
- Highway
- Limits
- Patching at 2 locations: 1) IL 13 east of Greenbriar Road; 2) IL 13 west of IL 148.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $39,862 | ||
| 2 | E. T. Simonds Construction Company | $76,505 | +91.9% | |
| 3 | G. M. Sipes Construction, Inc. | $79,020 | +98.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 E. T. Simonds C… | #3 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|
| 1 | 44200610 | CL A PATCH T2 13 | 22 | SQ YD | $250.00 | $561.27 | $550.00 | |
| 2 | 44201007 | CL B PATCH T2 13 | 44 | SQ YD | $375.00 | $531.31 | $550.00 | |
| 3 | 44201299 | DOWEL BARS 1 1/2 | 80 | EACH | $5.00 | $22.94 | $25.00 | |
| 4 | 44213000 | PATCH REINFORCEMENT | 22 | SQ YD | $30.00 | $59.00 | $60.00 | |
| 5 | 44213200 | SAW CUTS | 200 | FOOT | $8.00 | $24.88 | $15.00 | |
| 6 | 67100100 | MOBILIZATION | 1 | L SUM | $11,000.00 | $7,243.38 | $12,000.00 | |
| 7 | 70100320 | TRAF CONT-PROT 701422 | 1 | L SUM | $1.00 | $0.00 | $0.00 | |
| 8 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $1.00 | $20,188.91 | $19,000.00 | |
| 9 | 70107025 | CHANGEABLE MESSAGE SN | 40 | CAL DA | $75.00 | $64.40 | $10.00 | |
| 10 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $1,200.00 | $2,661.56 | $5,000.00 |