133B-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | E. T. Simonds Construction Company Low bidder | $2,284,273 | ||
| 2 | Samron Midwest Contracting, Inc. | $2,780,995 | +21.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 E. T. Simonds C… | #2 Samron Midwest … |
|---|---|---|---|---|---|---|---|
| 1 | Z0016702 | DETOUR SIGNING | 1 | L SUM | $7,158.47 | $25,000.00 | |
| 2 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | |
| 3 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 4 | 20100500 | TREE REMOV ACRES | 0.25 | ACRE | $32,569.12 | $35,000.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 190 | CU YD | $34.43 | $50.00 | |
| 6 | 20300100 | CHANNEL EXCAVATION | 1,708 | CU YD | $25.87 | $45.00 | |
| 7 | 25000200 | SEEDING CL 2 | 0.09 | ACRE | $27,582.56 | $25,000.00 | |
| 8 | 25000400 | NITROGEN FERT NUTR | 10 | POUND | $3.30 | $10.00 | |
| 9 | 25000500 | PHOSPHORUS FERT NUTR | 10 | POUND | $3.30 | $10.00 | |
| 10 | 25000600 | POTASSIUM FERT NUTR | 10 | POUND | $3.30 | $10.00 | |
| 11 | 25000700 | AGR GROUND LIMESTONE | 0.2 | TON | $220.00 | $2,500.00 | |
| 12 | 25100115 | MULCH METHOD 2 | 0.09 | ACRE | $27,582.56 | $0.0100 | |
| 13 | 25100630 | EROSION CONTR BLANKET | 413 | SQ YD | $5.97 | $3.00 | |
| 14 | 28000250 | TEMP EROS CONTR SEED | 240 | POUND | $5.87 | $0.0100 | |
| 15 | 28000305 | TEMP DITCH CHECKS | 74 | FOOT | $28.08 | $12.00 | |
| 16 | 28000400 | PERIMETER EROS BAR | 576 | FOOT | $6.18 | $5.00 | |
| 17 | 28100109 | STONE RIPRAP CL A5 | 1,405 | SQ YD | $69.57 | $85.00 | |
| 18 | 28200200 | FILTER FABRIC | 1,405 | SQ YD | $2.69 | $5.00 | |
| 19 | 35100700 | AGG BASE CSE A 8 | 1,067 | SQ YD | $19.20 | $15.00 | |
| 20 | 40600275 | BIT MATLS PR CT | 2,400 | POUND | $0.0100 | $0.0100 | |
| 21 | 40600290 | BIT MATLS TACK CT | 236 | POUND | $0.0100 | $0.0100 | |
| 22 | 40603080 | HMA BC IL-19.0 N50 | 89 | TON | $200.12 | $220.00 | |
| 23 | 40604052 | HMA SC IL-9.5 C N70 | 54 | TON | $203.63 | $300.00 | |
| 24 | 44000100 | PAVEMENT REM | 766 | SQ YD | $20.95 | $20.00 | |
| 25 | 48203013 | HMA SHOULDERS 4 | 409 | SQ YD | $38.41 | $30.00 | |
| 26 | 50100100 | REM EXIST STRUCT | 1 | EACH | $121,867.73 | $225,000.00 | |
| 27 | 50200100 | STRUCTURE EXCAVATION | 156 | CU YD | $20.60 | $100.00 | |
| 28 | 50200300 | COFFERDAM EXCAVATION | 161 | CU YD | $64.24 | $150.00 | |
| 29 | 50201121 | COFFERDAM TYP 2 LOC 1 | 1 | EACH | $156,202.42 | $338,000.00 | |
| 30 | 50300225 | CONC STRUCT | 139.2 | CU YD | $1,425.70 | $1,200.00 | |
| 31 | 50300255 | CONC SUP-STR | 131.2 | CU YD | $1,634.23 | $2,100.00 | |
| 32 | 50300260 | BR DECK GROOVING | 417 | SQ YD | $17.36 | $20.00 | |
| 33 | 50300300 | PROTECTIVE COAT | 493 | SQ YD | $4.13 | $2.50 | |
| 34 | 50500105 | F & E STRUCT STEEL | 1 | L SUM | $452,489.35 | $450,000.00 | |
| 35 | 50500505 | STUD SHEAR CONNECTORS | 2,670 | EACH | $3.71 | $4.00 | |
| 36 | 50800205 | REINF BARS, EPOXY CTD | 64,090 | POUND | $2.17 | $2.20 | |
| 37 | 50800530 | MECHANICAL SPLICERS | 200 | EACH | $95.67 | $75.00 | |
| 38 | 50900211 | STEEL RAILING TY IL-OH | 296 | FOOT | $623.70 | $600.00 | |
| 39 | 51202100 | FUR STL PILE HP14X117 | 1,899 | FOOT | $132.52 | $150.00 | |
| 40 | 51202305 | DRIVING PILES | 1,899 | FOOT | $0.0100 | $0.0100 | |
| 41 | 51204100 | TEST PILE ST HP14X117 | 2 | EACH | $10,352.69 | $15,000.00 | |
| 42 | 51204650 | PILE SHOES | 38 | EACH | $148.50 | $150.00 | |
| 43 | 51500100 | NAME PLATES | 1 | EACH | $780.71 | $350.00 | |
| 44 | 52100520 | ANCHOR BOLTS 1 | 30 | EACH | $118.77 | $125.00 | |
| 45 | 59300100 | CONTR LOW-STRENG MATL | 128 | CU YD | $153.14 | $200.00 | |
| 46 | 63000001 | SPBGR TY A 6FT POSTS | 25 | FOOT | $55.00 | $50.00 | |
| 47 | 63100117 | TRAF BAR TERM T13 | 4 | EACH | $4,620.00 | $5,300.00 | |
| 48 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $4,180.00 | $5,100.00 | |
| 49 | 63200310 | GUARDRAIL REMOV | 295 | FOOT | $5.50 | $25.00 | |
| 50 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,000.00 | $2,000.00 | |
| 51 | 67100100 | MOBILIZATION | 1 | L SUM | $127,466.12 | $160,000.00 | |
| 52 | 70107025 | CHANGEABLE MESSAGE SN | 42 | CAL DA | $46.15 | $100.00 | |
| 53 | 72400330 | REMOV SIGN PANEL T3 | 12 | SQ FT | $11.04 | $25.00 | |
| 54 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $55.00 | $55.00 | |
| 55 | 78009004 | MOD URETH PM LINE 4 | 1,230 | FOOT | $9.80 | $10.00 | |
| 56 | 78300200 | RAISED REF PVT MK REM | 10 | EACH | $15.65 | $40.00 |