22B-4
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sierra Bravo Contractors, LLC Low bidder | $361,879 | ||
| 2 | Samron Midwest Contracting, Inc. | $366,785 | +1.4% | |
| 3 | E. T. Simonds Construction Company | $419,754 | +16.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sierra Bravo Co… | #2 Samron Midwest … | #3 E. T. Simonds C… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0327979 | PAVMT MRKG REM GRIND | 559 | SQ FT | $5.00 | $2.00 | $0.00 | |
| 2 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $2,500.00 | $3,000.00 | $14,074.75 | |
| 3 | Z0007601 | BLDG REMOV NO 1 | 1 | L SUM | $4,761.15 | $3,200.00 | $6,810.10 | |
| 4 | 20100500 | TREE REMOV ACRES | 2.4 | ACRE | $8,677.88 | $10,000.00 | $8,103.00 | |
| 5 | 20200100 | EARTH EXCAVATION | 30,308 | CU YD | $3.99 | $4.50 | $4.59 | |
| 6 | 20200200 | ROCK EXCAVATION | 344 | CU YD | $52.99 | $35.00 | $60.94 | |
| 7 | 25000200 | SEEDING CL 2 | 2.3 | ACRE | $1,775.00 | $1,950.00 | $920.00 | |
| 8 | 25000350 | SEEDING CL 7 | 2.3 | ACRE | $775.00 | $850.00 | $690.00 | |
| 9 | 25000400 | NITROGEN FERT NUTR | 406 | POUND | $1.15 | $1.20 | $2.30 | |
| 10 | 25000500 | PHOSPHORUS FERT NUTR | 204 | POUND | $1.15 | $1.20 | $2.30 | |
| 11 | 25000600 | POTASSIUM FERT NUTR | 204 | POUND | $1.15 | $1.20 | $2.30 | |
| 12 | 25000700 | AGR GROUND LIMESTONE | 4.3 | TON | $210.00 | $235.00 | $115.00 | |
| 13 | 25100115 | MULCH METHOD 2 | 4.3 | ACRE | $1,450.00 | $1,600.00 | $920.00 | |
| 14 | 28000250 | TEMP EROS CONTR SEED | 424 | POUND | $1.00 | $0.00 | $4.60 | |
| 15 | 28000305 | TEMP DITCH CHECKS | 382 | FOOT | $15.00 | $20.00 | $17.25 | |
| 16 | 28000500 | INLET & PIPE PROTECT | 2 | EACH | $125.00 | $125.00 | $192.04 | |
| 17 | 28001100 | TEMP EROS CONTR BLANK | 1,262 | SQ YD | $1.85 | $1.15 | $2.13 | |
| 18 | 31101000 | SUB GRAN MAT B | 26 | TON | $55.65 | $30.00 | $35.81 | |
| 19 | 35101400 | AGG BASE CSE B | 1,058 | TON | $21.92 | $20.00 | $24.34 | |
| 20 | 40600290 | BIT MATLS TACK CT | 3,592 | POUND | $0.0100 | $0.00 | $0.00 | |
| 21 | 40600982 | HMA SURF REM BUTT JT | 200 | SQ YD | $34.90 | $3.00 | $32.11 | |
| 22 | 40600990 | TEMPORARY RAMP | 35 | SQ YD | $32.32 | $10.00 | $52.22 | |
| 23 | 40604052 | HMA SC IL-9.5 C N70 | 302 | TON | $128.19 | $110.00 | $122.08 | |
| 24 | 44000100 | PAVEMENT REM | 469 | SQ YD | $12.15 | $10.00 | $13.33 | |
| 25 | 48101200 | AGGREGATE SHLDS B | 170 | TON | $61.20 | $35.00 | $70.38 | |
| 26 | 50100100 | REM EXIST STRUCT | 1 | EACH | $26,494.32 | $40,000.00 | $41,153.73 | |
| 27 | 50105220 | PIPE CULVERT REMOV | 65 | FOOT | $21.86 | $10.00 | $32.63 | |
| 28 | 63100045 | TRAF BAR TERM T2 | 4 | EACH | $2,305.00 | $2,100.00 | $2,650.75 | |
| 29 | 63200310 | GUARDRAIL REMOV | 376 | FOOT | $7.84 | $11.00 | $20.30 | |
| 30 | 66600105 | FUR ERECT ROW MARKERS | 4 | EACH | $100.00 | $200.00 | $115.00 | |
| 31 | 67100100 | MOBILIZATION | 1 | L SUM | $21,639.26 | $22,000.00 | $35,616.83 | |
| 32 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $3,800.00 | $9,200.00 | $0.00 | |
| 33 | 70107025 | CHANGEABLE MESSAGE SN | 56 | CAL DA | $100.00 | $80.00 | $57.76 | |
| 34 | 70300100 | SHORT TERM PAVT MKING | 52 | FOOT | $1.00 | $2.00 | $1.09 | |
| 35 | 70300150 | SHRT TRM PAVT MK REM | 18 | SQ FT | $12.57 | $4.00 | $12.38 | |
| 36 | 70300220 | TEMP PVT MK LINE 4 | 1,281 | FOOT | $2.68 | $0.00 | $0.00 | |
| 37 | 70300280 | TEMP PVT MK LINE 24 | 30 | FOOT | $16.10 | $0.00 | $0.00 | |
| 38 | 72000100 | SIGN PANEL T1 | 31 | SQ FT | $25.00 | $36.00 | $28.75 | |
| 39 | 72900100 | METAL POST TY A | 96 | FOOT | $12.00 | $10.00 | $13.80 | |
| 40 | 78001110 | PAINT PVT MK LINE 4 | 1,281 | FOOT | $2.68 | $2.65 | $3.14 | |
| 41 | 78001180 | PAINT PVT MK LINE 24 | 30 | FOOT | $16.10 | $11.00 | $11.67 |