(57,113)PP
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Christ Bros. Asphalt, Inc. Low bidder | $267,960 | ||
| 2 | Kinney Contractors, Inc. | $307,717 | +14.8% | |
| 3 | Stutz Excavating, Inc. | $428,513 | +59.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Christ Bros. As… | #2 Kinney Contract… | #3 Stutz Excavatin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X4406230 | PART DEP REM T2 3 | 174 | SQ YD | $33.58 | $80.00 | $89.75 | |
| 2 | X4406430 | PART DEP REM T3 3 | 536 | SQ YD | $33.58 | $56.00 | $89.75 | |
| 3 | X4406630 | PART DEP REM T4 3 | 160 | SQ YD | $33.58 | $54.00 | $89.75 | |
| 4 | X4421000 | PARTIAL DEPTH PATCH | 146 | TON | $314.72 | $330.00 | $585.00 | |
| 5 | 44201815 | CL D PATCH T2 14 | 26 | SQ YD | $252.00 | $275.00 | $434.00 | |
| 6 | 44201819 | CL D PATCH T3 14 | 48 | SQ YD | $252.00 | $273.00 | $434.00 | |
| 7 | 44201821 | CL D PATCH T4 14 | 408 | SQ YD | $252.00 | $271.00 | $434.00 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $26,863.00 | $20,000.00 | $27,500.00 | |
| 9 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $5,540.00 | $33,600.00 | $5,800.00 | |
| 10 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $28,706.00 | $1.00 | $1,000.00 | |
| 11 | 70107025 | CHANGEABLE MESSAGE SN | 82 | CAL DA | $65.00 | $40.00 | $68.00 | |
| 12 | 70300100 | SHORT TERM PAVT MKING | 2,167 | FOOT | $0.0100 | $3.00 | $1.50 | |
| 13 | 70300150 | SHRT TRM PAVT MK REM | 722 | SQ FT | $0.0100 | $10.00 | $2.50 | |
| 14 | 78001110 | PAINT PVT MK LINE 4 | 3,583 | FOOT | $1.00 | $1.10 | $1.10 | |
| 15 | 78100100 | RAISED REFL PAVT MKR | 12 | EACH | $106.75 | $115.00 | $535.00 | |
| 16 | 78300200 | RAISED REF PVT MK REM | 12 | EACH | $0.0100 | $18.00 | $45.00 |