82-(6,7,8)PP-1
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Christ Bros. Asphalt, Inc. Low bidder | $647,720 | ||
| 2 | The Kilian Corporation | $740,830 | +14.4% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Christ Bros. As… | #2 The Kilian Corp… |
|---|---|---|---|---|---|---|---|
| 1 | X1700055 | CL A PATCH T2 13 SPL | 16 | SQ YD | $247.90 | $260.00 | |
| 2 | X1700056 | CL A PATCH T3 13 SPL | 32 | SQ YD | $247.90 | $260.00 | |
| 3 | X1700079 | CL A PATCH T3 12 SPL | 40 | SQ YD | $215.80 | $225.00 | |
| 4 | X4406020 | PART DEP REM T1 2 | 7 | SQ YD | $29.11 | $110.00 | |
| 5 | X4406220 | PART DEP REM T2 2 | 264 | SQ YD | $29.11 | $89.00 | |
| 6 | X4406420 | PART DEP REM T3 2 | 375 | SQ YD | $29.11 | $72.00 | |
| 7 | X4406620 | PART DEP REM T4 2 | 2,497 | SQ YD | $29.11 | $58.00 | |
| 8 | X4420579 | CL A PATCH T4 12 SPL | 233 | SQ YD | $213.90 | $223.00 | |
| 9 | X4420621 | CL A PATCH T2 14 SPL | 16 | SQ YD | $223.15 | $233.00 | |
| 10 | X4420628 | CL A PATCH T4 14 SPL | 67 | SQ YD | $223.15 | $233.00 | |
| 11 | X4420630 | CL A PATCH T2 15 SPL | 8 | SQ YD | $228.00 | $239.00 | |
| 12 | X4420632 | CL A PATCH T3 15 SPL | 16 | SQ YD | $228.00 | $239.00 | |
| 13 | X4421000 | PARTIAL DEPTH PATCH | 363 | TON | $336.33 | $205.00 | |
| 14 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 15 | 44213000 | PATCH REINFORCEMENT | 428 | SQ YD | $78.90 | $82.00 | |
| 16 | 44213200 | SAW CUTS | 1,206 | FOOT | $7.15 | $7.50 | |
| 17 | 44213204 | TIE BARS 3/4 | 75 | EACH | $11.90 | $12.50 | |
| 18 | 67100100 | MOBILIZATION | 1 | L SUM | $62,011.00 | $44,000.00 | |
| 19 | 70100420 | TRAF CONT-PROT 701411 | 7 | EACH | $1,750.00 | $2,750.00 | |
| 20 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $8,970.00 | $0.0100 | |
| 21 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $88,980.00 | $153,000.00 | |
| 22 | 70100815 | TRAF CONT-PROT 701446 | 1 | L SUM | $8,980.00 | $7,000.00 | |
| 23 | 70107025 | CHANGEABLE MESSAGE SN | 826 | CAL DA | $40.00 | $50.00 | |
| 24 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $38,163.00 | $18,500.00 | |
| 25 | 70300100 | SHORT TERM PAVT MKING | 967 | FOOT | $3.50 | $3.00 | |
| 26 | 70300150 | SHRT TRM PAVT MK REM | 317 | SQ FT | $15.75 | $12.00 | |
| 27 | 78000400 | THPL PVT MK LINE 6 | 1,398 | FOOT | $7.50 | $7.85 | |
| 28 | 78001130 | PAINT PVT MK LINE 6 | 1,279 | FOOT | $2.60 | $2.70 | |
| 29 | 78100100 | RAISED REFL PAVT MKR | 255 | EACH | $56.50 | $59.00 | |
| 30 | 78300200 | RAISED REF PVT MK REM | 255 | EACH | $0.0100 | $0.0100 |