(104,107)RS-3
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illinois Valley Paving, a div of UCM, Inc. Low bidder | $882,674 | ||
| 2 | Charles E. Mahoney Co. | $913,562 | +3.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illinois Valley… | #2 Charles E. Maho… |
|---|---|---|---|---|---|---|---|
| 1 | X7030005 | TEMP PAVT MKING REMOV | 14,917 | SQ FT | $0.0100 | $0.00 | |
| 2 | Z0033700 | LONG JOINT SEALANT | 16,955 | FOOT | $2.65 | $2.68 | |
| 3 | Z0034105 | MATL TRANSFER DEVICE | 4,110 | TON | $3.34 | $7.68 | |
| 4 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | |
| 5 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 6 | 40600290 | BIT MATLS TACK CT | 22,008 | POUND | $1.59 | $1.18 | |
| 7 | 40600990 | TEMPORARY RAMP | 92 | SQ YD | $13.08 | $34.32 | |
| 8 | 40604052 | HMA SC IL-9.5 C N70 | 4,110 | TON | $106.81 | $115.29 | |
| 9 | 44000155 | HMA SURF REM 1 1/2 | 48,904 | SQ YD | $3.45 | $2.68 | |
| 10 | 44200168 | PAVT PATCH T2 14 | 172 | SQ YD | $237.37 | $189.42 | |
| 11 | 48102100 | AGG WEDGE SHLD TYPE B | 648 | TON | $24.64 | $27.83 | |
| 12 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $2,978.19 | $2,852.02 | |
| 13 | 67100100 | MOBILIZATION | 1 | L SUM | $20,619.05 | $53,587.50 | |
| 14 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $15,400.00 | $14,000.00 | |
| 15 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $16,555.00 | $15,050.00 | |
| 16 | 70300100 | SHORT TERM PAVT MKING | 4,680 | FOOT | $1.19 | $1.39 | |
| 17 | 70300150 | SHRT TRM PAVT MK REM | 524 | SQ FT | $5.11 | $10.67 | |
| 18 | 70300220 | TEMP PVT MK LINE 4 | 44,741 | FOOT | $0.0100 | $0.00 | |
| 19 | 78000200 | THPL PVT MK LINE 4 | 44,741 | FOOT | $0.7000 | $0.6400 | |
| 20 | 78100100 | RAISED REFL PAVT MKR | 218 | EACH | $42.92 | $39.02 | |
| 21 | 78300200 | RAISED REF PVT MK REM | 218 | EACH | $20.14 | $16.43 |