95-(3,4,5)PP-1
- Let date
- Friday, November 6, 2020
- Contract
- 76N94 · job page
- District
- District 8
- County
- Washington
- Highway
- Limits
- 11.6 miles of patching on I-64 from 0.5 miles west of Beaver Pond Creek to 1.4 miles east of CH 11.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kinney Contractors, Inc. Low bidder | $989,201 | ||
| 2 | Keeley & Sons, Inc. | $992,776 | +0.4% | |
| 3 | G. M. Sipes Construction, Inc. | $1,007,752 | +1.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kinney Contract… | #2 Keeley & Sons, … | #3 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|
| 1 | X4406240 | PART DEP REM T2 4 | 510 | SQ YD | $130.00 | $119.34 | $125.00 | |
| 2 | X4406440 | PART DEP REM T3 4 | 1,076 | SQ YD | $100.00 | $89.76 | $93.00 | |
| 3 | X4406640 | PART DEP REM T4 4 | 1,336 | SQ YD | $74.00 | $66.30 | $69.00 | |
| 4 | X4421000 | PARTIAL DEPTH PATCH | 653.8 | TON | $175.00 | $168.30 | $217.49 | |
| 5 | Z0076604 | TRAINEES TPG | 1,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 6 | 44200577 | CL A PATCH T2 12 | 369 | SQ YD | $250.00 | $269.80 | $275.00 | |
| 7 | 44200581 | CL A PATCH T3 12 | 228 | SQ YD | $248.00 | $269.80 | $265.00 | |
| 8 | 44200583 | CL A PATCH T4 12 | 652 | SQ YD | $246.00 | $269.80 | $255.00 | |
| 9 | 44213000 | PATCH REINFORCEMENT | 1,249 | SQ YD | $60.00 | $57.15 | $75.00 | |
| 10 | 44213200 | SAW CUTS | 5,120 | FOOT | $7.00 | $5.01 | $3.00 | |
| 11 | 44213204 | TIE BARS 3/4 | 238 | EACH | $15.00 | $11.80 | $5.00 | |
| 12 | 67100100 | MOBILIZATION | 1 | L SUM | $50,000.00 | $73,550.00 | $45,000.00 | |
| 13 | 70100420 | TRAF CONT-PROT 701411 | 4 | EACH | $2,000.00 | $1,980.00 | $500.00 | |
| 14 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $1.00 | $23,980.00 | $1.00 | |
| 15 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $73,500.00 | $49,890.00 | $75,000.00 | |
| 16 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $15,000.00 | $9,975.60 | $15,000.00 | |
| 17 | 78001110 | PAINT PVT MK LINE 4 | 5,490 | FOOT | $1.50 | $1.81 | $1.77 | |
| 18 | 78100100 | RAISED REFL PAVT MKR | 35 | EACH | $250.00 | $275.61 | $270.20 |