Bid tab 76L90

Let Apr 24, 2020 · District 8 · Marion Sign up free

‹ Apr 2020 results

61-(1,2,3,4,5,6)PP-1

Let date
Friday, April 24, 2020
Contract
76L90 · job page
District
District 8
County
Marion
Highway
Limits
28 miles of patching on I-57 from the Jefferson County line to the Fayette County line.

Bidders 3

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Beniach Construction Co., Inc. Low bidder $1,302,348
2 Kinney Contractors, Inc. $1,374,767 +5.6%
3 G. M. Sipes Construction, Inc. $1,402,132 +7.7%

Bid tab: unit prices 12 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Beniach Constru…#2 Kinney Contract…#3 G. M. Sipes Con…
1Z0076604 TRAINEES TPG500HOUR $15.00 $15.00 $15.00
244200610 CL A PATCH T2 131,344SQ YD $193.00 $188.00 $200.00
344200612 CL A PATCH T3 13518SQ YD $187.00 $165.00 $200.00
444200614 CL A PATCH T4 133,142SQ YD $185.00 $153.00 $175.00
544213000 PATCH REINFORCEMENT5,004SQ YD $38.00 $55.00 $55.00
644213200 SAW CUTS20,790FOOT $0.0100 $4.00 $1.00
744213204 TIE BARS 3/43,416EACH $7.00 $14.00 $1.00
867100100 MOBILIZATION1L SUM $64,000.00 $30,000.00 $65,000.00
970100420 TRAF CONT-PROT 70141116EACH $0.0100 $900.00 $1.00
1070100700 TRAF CONT-PROT 7014061L SUM $0.0100 $2,500.00 $1.00
1170100800 TRAF CONT-PROT 7014011L SUM $71,800.00 $88,500.00 $90,000.00
1278001110 PAINT PVT MK LINE 42,265FOOT $3.20 $3.00 $7.92