DIST 8 PATCHING 2018-2
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Beniach Construction Co., Inc. Low bidder | $633,392 | ||
| 2 | Kinney Contractors, Inc. | $656,960 | +3.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Beniach Constru… | #2 Kinney Contract… |
|---|---|---|---|---|---|---|---|
| 1 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | |
| 2 | 44200525 | CL A PATCH T1 8 | 213 | SQ YD | $153.00 | $165.00 | |
| 3 | 44200529 | CL A PATCH T2 8 | 1,023 | SQ YD | $125.00 | $155.00 | |
| 4 | 44200533 | CL A PATCH T3 8 | 703 | SQ YD | $119.00 | $152.00 | |
| 5 | 44200535 | CL A PATCH T4 8 | 1,060 | SQ YD | $118.00 | $139.00 | |
| 6 | 44213000 | PATCH REINFORCEMENT | 2,964 | SQ YD | $38.00 | $42.00 | |
| 7 | 44213200 | SAW CUTS | 15,378 | FOOT | $3.40 | $0.1000 | |
| 8 | 44213204 | TIE BARS 3/4 | 526 | EACH | $7.50 | $11.00 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $32,000.00 | $14,000.00 | |
| 10 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $0.0100 | $4,000.00 | |
| 11 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $39,400.00 | $33,900.00 | |
| 12 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $0.0100 | $4,000.00 | |
| 13 | 70102622 | TR CONT & PROT 701502 | 1 | L SUM | $0.0100 | $2,000.00 | |
| 14 | 78001110 | PAINT PVT MK LINE 4 | 5,692 | FOOT | $0.4000 | $0.2800 | |
| 15 | 78100100 | RAISED REFL PAVT MKR | 244 | EACH | $58.00 | $42.00 |