60-7PS-2
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Davinroy Mechanical Contractor, Inc. Low bidder | $182,000 | ||
| 2 | Haier Plumbing and Heating, Inc. | $187,812 | +3.2% | |
| 3 | Korte and Luitjohan Contractors, Inc. | $190,900 | +4.9% |
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Davinroy Mechanical Contractor, Inc. Low bidder | $182,000 | ||
| 2 | Haier Plumbing and Heating, Inc. | $187,812 | +3.2% | |