(20-1,18)RS-4
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Howell Paving, Inc. Low bidder | $1,912,983 | ||
| 2 | The Kilian Corporation | $2,275,911 | +19.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Howell Paving, … | #2 The Kilian Corp… |
|---|---|---|---|---|---|---|---|
| 1 | X7030005 | TEMP PAVT MKING REMOV | 12,005 | SQ FT | $0.00 | $0.00 | |
| 2 | Z0033700 | LONG JOINT SEALANT | 18,690 | FOOT | $2.64 | $2.50 | |
| 3 | Z0034105 | MATL TRANSFER DEVICE | 6,702 | TON | $1.59 | $5.00 | |
| 4 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $5,000.00 | $1,450.00 | |
| 5 | Z0054517 | ROCK FILL - FOUNDATN | 36 | TON | $67.15 | $95.00 | |
| 6 | Z0070100 | SURV MONUMENT COV ASY | 1 | EACH | $199.48 | $150.00 | |
| 7 | Z0076600 | TRAINEES | 1,500 | HOUR | $0.8000 | $0.8000 | |
| 8 | Z0076604 | TRAINEES TPG | 1,500 | HOUR | $15.00 | $15.00 | |
| 9 | 20200100 | EARTH EXCAVATION | 190 | CU YD | $47.50 | $95.00 | |
| 10 | 20200600 | EXC & GR EX SHOULDER | 317 | UNIT | $198.54 | $90.00 | |
| 11 | 20400800 | FURNISHED EXCAVATION | 65 | CU YD | $74.70 | $75.00 | |
| 12 | 20700220 | POROUS GRAN EMBANK | 21 | CU YD | $59.65 | $75.00 | |
| 13 | 25000200 | SEEDING CL 2 | 0.25 | ACRE | $14,672.16 | $9,850.00 | |
| 14 | 25000400 | NITROGEN FERT NUTR | 23 | POUND | $1.15 | $1.25 | |
| 15 | 25000500 | PHOSPHORUS FERT NUTR | 23 | POUND | $1.15 | $1.25 | |
| 16 | 25000600 | POTASSIUM FERT NUTR | 23 | POUND | $1.15 | $1.25 | |
| 17 | 25100115 | MULCH METHOD 2 | 0.75 | ACRE | $1,875.00 | $2,000.00 | |
| 18 | 25100630 | EROSION CONTR BLANKET | 1,133 | SQ YD | $1.45 | $1.60 | |
| 19 | 28000250 | TEMP EROS CONTR SEED | 42 | POUND | $8.85 | $5.00 | |
| 20 | 28000305 | TEMP DITCH CHECKS | 211 | FOOT | $27.60 | $15.00 | |
| 21 | 28000400 | PERIMETER EROS BAR | 725 | FOOT | $4.85 | $5.00 | |
| 22 | 28100107 | STONE RIPRAP CL A4 | 452 | SQ YD | $63.90 | $78.00 | |
| 23 | 28200200 | FILTER FABRIC | 450 | SQ YD | $9.45 | $1.25 | |
| 24 | 40600290 | BIT MATLS TACK CT | 37,727 | POUND | $0.9000 | $1.25 | |
| 25 | 40600990 | TEMPORARY RAMP | 261 | SQ YD | $6.23 | $0.0100 | |
| 26 | 40602975 | HMA BC IL-9.5FG N90 | 3,046 | TON | $79.45 | $97.00 | |
| 27 | 40604064 | HMA SC IL-9.5 D N90 | 3,656 | TON | $85.80 | $101.00 | |
| 28 | 44000160 | HMA SURF REM 2 3/4 | 45,329 | SQ YD | $2.53 | $3.05 | |
| 29 | 44004250 | PAVED SHLD REMOVAL | 5,281 | SQ YD | $1.00 | $6.25 | |
| 30 | 44200202 | PAVT PATCH T2 17 | 75 | SQ YD | $201.72 | $299.00 | |
| 31 | 44200204 | PAVT PATCH T3 17 | 22 | SQ YD | $180.04 | $274.00 | |
| 32 | 44200206 | PAVT PATCH T4 17 | 1,208 | SQ YD | $146.24 | $197.00 | |
| 33 | 44300200 | STRIP REF CR CON TR | 2,508 | FOOT | $3.94 | $1.25 | |
| 34 | 48101200 | AGGREGATE SHLDS B | 483 | TON | $25.18 | $28.00 | |
| 35 | 48102100 | AGG WEDGE SHLD TYPE B | 693 | TON | $26.37 | $28.00 | |
| 36 | 48203029 | HMA SHOULDERS 8 | 10,563 | SQ YD | $33.25 | $50.00 | |
| 37 | 48203100 | HMA SHOULDERS | 279 | TON | $99.82 | $94.00 | |
| 38 | 50105220 | PIPE CULVERT REMOV | 19 | FOOT | $42.50 | $16.00 | |
| 39 | 50800105 | REINFORCEMENT BARS | 3,420 | POUND | $4.70 | $2.25 | |
| 40 | 54001001 | BOX CUL END SEC C1 | 1 | EACH | $4,870.00 | $9,600.00 | |
| 41 | 54001002 | BOX CUL END SEC C2 | 1 | EACH | $4,870.00 | $8,950.00 | |
| 42 | 54003000 | CONC BOX CUL | 16.4 | CU YD | $3,990.00 | $3,300.00 | |
| 43 | 54010303 | PCBC 3X3 | 9 | FOOT | $1,980.00 | $1,325.00 | |
| 44 | 63000003 | SPBGR TY A 9FT POSTS | 575 | FOOT | $30.55 | $31.50 | |
| 45 | 63000350 | LSG OV CUL 12'6" SPAN | 75 | FOOT | $33.35 | $34.50 | |
| 46 | 63000360 | LSG OV CUL 18'9" SPAN | 87.5 | FOOT | $33.35 | $34.50 | |
| 47 | 63100167 | TR BAR TRM T1 SPL TAN | 8 | EACH | $3,095.00 | $3,200.00 | |
| 48 | 63200310 | GUARDRAIL REMOV | 670 | FOOT | $12.94 | $9.00 | |
| 49 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $2,728.00 | $2,200.00 | |
| 50 | 67100100 | MOBILIZATION | 1 | L SUM | $94,548.31 | $90,800.00 | |
| 51 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $0.00 | $2,000.00 | |
| 52 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $30,000.00 | $35,000.00 | |
| 53 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $15,000.00 | $13,000.00 | |
| 54 | 70100600 | TRAF CONT-PROT 701336 | 1 | L SUM | $14,500.00 | $0.00 | |
| 55 | 70300100 | SHORT TERM PAVT MKING | 8,649 | FOOT | $0.00 | $0.0100 | |
| 56 | 70300150 | SHRT TRM PAVT MK REM | 961 | SQ FT | $0.00 | $0.0100 | |
| 57 | 70300210 | TEMP PVT MK LTR & SYM | 200 | SQ FT | $0.00 | $0.00 | |
| 58 | 70300220 | TEMP PVT MK LINE 4 | 35,066 | FOOT | $0.00 | $0.00 | |
| 59 | 70300280 | TEMP PVT MK LINE 24 | 58 | FOOT | $0.00 | $0.00 | |
| 60 | 72501000 | TERMINAL MARKER - DA | 8 | EACH | $25.00 | $31.00 | |
| 61 | 78000100 | THPL PVT MK LTR & SYM | 200 | SQ FT | $5.00 | $10.25 | |
| 62 | 78000200 | THPL PVT MK LINE 4 | 35,066 | FOOT | $0.8300 | $0.5000 | |
| 63 | 78000650 | THPL PVT MK LINE 24 | 58 | FOOT | $5.50 | $25.00 | |
| 64 | 78100100 | RAISED REFL PAVT MKR | 199 | EACH | $35.00 | $37.00 | |
| 65 | 78200005 | GRDRAIL REF TYPE A | 17 | EACH | $9.00 | $9.50 | |
| 66 | 78300200 | RAISED REF PVT MK REM | 199 | EACH | $6.63 | $5.00 |