15BR-1
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sierra Bravo Contractors, LLC Low bidder | $605,373 | ||
| 2 | Plocher Construction Company, Inc. | $667,900 | +10.3% | |
| 3 | Samron Midwest Contracting, Inc. | $688,631 | +13.8% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sierra Bravo Co… | #2 Plocher Constru… | #3 Samron Midwest … |
|---|---|---|---|---|---|---|---|---|
| 1 | X0900064 | MEMBR WTRPR SYS B STR | 119 | SQ YD | $39.14 | $50.65 | $60.00 | |
| 2 | X6660445 | ROW/PROPERTY CORNERS | 5 | EACH | $780.00 | $400.00 | $325.00 | |
| 3 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $5,200.00 | $1,500.00 | $2,200.00 | |
| 4 | X7030005 | TEMP PAVT MKING REMOV | 376 | SQ FT | $15.68 | $1.00 | $0.00 | |
| 5 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $15,600.00 | $5,000.00 | $5,838.00 | |
| 6 | Z0033700 | LONG JOINT SEALANT | 1,006 | FOOT | $11.70 | $11.25 | $13.00 | |
| 7 | Z0054517 | ROCK FILL - FOUNDATN | 106 | TON | $47.76 | $50.00 | $41.00 | |
| 8 | Z0076600 | TRAINEES | 500 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 9 | Z0076604 | TRAINEES TPG | 500 | HOUR | $15.00 | $15.00 | $15.00 | |
| 10 | 20100500 | TREE REMOV ACRES | 0.25 | ACRE | $21,948.43 | $15,750.00 | $16,500.00 | |
| 11 | 20200100 | EARTH EXCAVATION | 538 | CU YD | $12.08 | $25.00 | $23.00 | |
| 12 | 20400800 | FURNISHED EXCAVATION | 820 | CU YD | $20.08 | $25.00 | $23.00 | |
| 13 | 20700220 | POROUS GRAN EMBANK | 105 | CU YD | $76.70 | $65.00 | $65.00 | |
| 14 | 25000210 | SEEDING CL 2A | 1 | ACRE | $3,276.00 | $3,150.00 | $3,650.00 | |
| 15 | 25000400 | NITROGEN FERT NUTR | 90 | POUND | $1.20 | $1.15 | $1.25 | |
| 16 | 25000500 | PHOSPHORUS FERT NUTR | 90 | POUND | $1.20 | $1.15 | $1.25 | |
| 17 | 25000600 | POTASSIUM FERT NUTR | 90 | POUND | $1.20 | $1.15 | $1.25 | |
| 18 | 25100115 | MULCH METHOD 2 | 2 | ACRE | $1,092.00 | $105.00 | $1,215.00 | |
| 19 | 28000250 | TEMP EROS CONTR SEED | 81 | POUND | $3.08 | $8.00 | $5.79 | |
| 20 | 28000305 | TEMP DITCH CHECKS | 96 | FOOT | $26.00 | $16.00 | $8.00 | |
| 21 | 28000400 | PERIMETER EROS BAR | 1,086 | FOOT | $3.07 | $2.10 | $3.40 | |
| 22 | 28001100 | TEMP EROS CONTR BLANK | 2,936 | SQ YD | $2.08 | $2.00 | $3.50 | |
| 23 | 28100107 | STONE RIPRAP CL A4 | 410 | SQ YD | $54.09 | $58.00 | $93.00 | |
| 24 | 28100109 | STONE RIPRAP CL A5 | 261 | SQ YD | $57.71 | $110.00 | $92.00 | |
| 25 | 28200200 | FILTER FABRIC | 671 | SQ YD | $2.08 | $2.50 | $5.80 | |
| 26 | 31100100 | SUB GRAN MAT A | 565 | TON | $35.42 | $45.00 | $45.00 | |
| 27 | 40600275 | BIT MATLS PR CT | 3,008 | POUND | $0.6300 | $0.6100 | $0.7100 | |
| 28 | 40700100 | BIT MATLS TACK CT | 1,204 | POUND | $0.5900 | $0.5700 | $0.6600 | |
| 29 | 40701841 | HMA PAVT FD 8 | 1,338 | SQ YD | $59.47 | $57.18 | $65.00 | |
| 30 | 44000100 | PAVEMENT REM | 1,157 | SQ YD | $9.65 | $12.00 | $8.75 | |
| 31 | 48100700 | AGGREGATE SHLDS A 8 | 208 | SQ YD | $25.79 | $30.00 | $25.00 | |
| 32 | 50100300 | REM EXIST STRUCT N1 | 1 | EACH | $14,440.00 | $20,000.00 | $15,000.00 | |
| 33 | 50200450 | REM/DISP UNS MATL-STR | 56 | CU YD | $56.66 | $32.00 | $58.00 | |
| 34 | 50800105 | REINFORCEMENT BARS | 26,650 | POUND | $1.24 | $1.20 | $1.35 | |
| 35 | 51500100 | NAME PLATES | 1 | EACH | $780.00 | $459.82 | $335.00 | |
| 36 | 54003000 | CONC BOX CUL | 127 | CU YD | $917.25 | $1,200.00 | $1,000.00 | |
| 37 | 54011210 | PCBC 12X10 | 52 | FOOT | $1,034.69 | $1,200.00 | $1,800.00 | |
| 38 | 59100100 | GEOCOMPOSITE WALL DR | 119 | SQ YD | $13.64 | $20.00 | $20.00 | |
| 39 | 63000001 | SPBGR TY A 6FT POSTS | 392 | FOOT | $26.31 | $19.00 | $25.00 | |
| 40 | 63000030 | SPGR ATT TO CULVERT | 59 | FOOT | $305.81 | $240.00 | $249.00 | |
| 41 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,146.00 | $2,500.00 | $4,000.00 | |
| 42 | 66600105 | FUR ERECT ROW MARKERS | 20 | EACH | $156.00 | $20.00 | $188.00 | |
| 43 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $1,976.00 | $650.00 | $1,500.00 | |
| 44 | 67100100 | MOBILIZATION | 1 | L SUM | $29,973.44 | $52,700.00 | $39,000.00 | |
| 45 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $2,600.00 | $20,000.00 | $4,800.00 | |
| 46 | 70107025 | CHANGEABLE MESSAGE SN | 150 | CAL DA | $93.60 | $30.00 | $72.00 | |
| 47 | 70300100 | SHORT TERM PAVT MKING | 100 | FOOT | $0.3700 | $0.3600 | $1.85 | |
| 48 | 70300150 | SHRT TRM PAVT MK REM | 33 | SQ FT | $28.52 | $7.00 | $1.27 | |
| 49 | 70300220 | TEMP PVT MK LINE 4 | 1,127 | FOOT | $3.62 | $0.0100 | $0.00 | |
| 50 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $46.80 | $30.00 | $50.00 | |
| 51 | 78000200 | THPL PVT MK LINE 4 | 1,127 | FOOT | $3.62 | $3.48 | $3.35 | |
| 52 | 78100100 | RAISED REFL PAVT MKR | 7 | EACH | $595.92 | $575.00 | $115.00 | |
| 53 | 78200005 | GRDRAIL REF TYPE A | 10 | EACH | $10.40 | $10.00 | $11.50 |