Bid tab 76J79

Let Apr 27, 2018 · District 8 · St. Clair Start free trial

‹ Apr 2018 results

50,52CLV-1

Let date
Friday, April 27, 2018
Contract
76J79 · job page
District
District 8
County
St. Clair
Highway
Limits
Extension of culvert SN 082-2406 on IL 4 from Jefferson Road to Moeller Road.
Classification
·
Project number

Bidders 2

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 CSD Environmental Services, Inc. Low bidder $59,486
2 Prado Construction $97,194 +63.4%

Bid tab: unit prices 18 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 CSD Environment…#2 Prado Construct…
1X0322128 MEMBR WTRPR B STRUCT19SQ YD $82.89 $523.52
220100110 TREE REMOV 6-1576UNIT $25.00 $20.22
320100210 TREE REMOV OVER 1550UNIT $38.00 $0.00
420200100 EARTH EXCAVATION50CU YD $21.20 $47.34
520400800 FURNISHED EXCAVATION410CU YD $28.15 $36.34
625000210 SEEDING CL 2A0.25ACRE $4,000.00 $3,889.98
725000400 NITROGEN FERT NUTR23POUND $1.50 $1.80
825000500 PHOSPHORUS FERT NUTR23POUND $1.50 $1.80
925000600 POTASSIUM FERT NUTR23POUND $1.50 $1.80
1028100107 STONE RIPRAP CL A413SQ YD $141.15 $75.76
1128200200 FILTER FABRIC13SQ YD $26.92 $7.30
1250102400 CONC REM0.2CU YD $1,500.00 $14,420.50
1350800105 REINFORCEMENT BARS3,000POUND $1.35 $3.80
1454002020 EXPAN BOLTS 3/424EACH $120.00 $88.42
1554003000 CONC BOX CUL17.8CU YD $876.00 $1,520.32
1666600105 FUR ERECT ROW MARKERS8EACH $150.00 $262.50
1767100100 MOBILIZATION1L SUM $7,748.33 $5,407.74
1870100450 TRAF CONT-PROT 7012011L SUM $6,450.00 $15,292.22