D7 EMULSION TANK 2024
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Samron Midwest Contracting, Inc. Low bidder | $222,222 | ||
| 2 | Sangamo Construction Company | $303,220 | +36.4% | |
| 3 | Kieffer Bros. Construction Co., Inc. | $309,062 | +39.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Samron Midwest … | #2 Sangamo Constru… | #3 Kieffer Bros. C… |
|---|---|---|---|---|---|---|---|---|
| 1 | XP000136 | 100A CIRCUIT BRKR 2P | 1 | EACH | $945.00 | $962.27 | $875.00 | |
| 2 | X1200131 | EMULSION TANK | 1 | L SUM | $155,368.22 | $189,615.85 | $194,000.00 | |
| 3 | X1400517 | SFY SW 60A NEMA 3R 2P | 1 | EACH | $2,200.00 | $2,352.22 | $2,098.00 | |
| 4 | X1400518 | SFY SW100A NEMA 3R 2P | 1 | EACH | $2,400.00 | $2,672.98 | $2,274.00 | |
| 5 | X8010260 | 60A CIRCUIT BREAKR 2P | 1 | EACH | $800.00 | $748.44 | $758.00 | |
| 6 | 50300225 | CONC STRUCT | 15.1 | CU YD | $1,650.00 | $1,563.91 | $4,414.00 | |
| 7 | 50800205 | REINF BARS, EPOXY CTD | 2,130 | POUND | $5.00 | $6.30 | $9.00 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $14,500.00 | $17,889.96 | $13,250.00 | |
| 9 | 81028320 | UNDRGRD C PVC 1 | 150 | FOOT | $10.00 | $97.66 | $9.90 | |
| 10 | 81028330 | UNDRGRD C PVC 1 1/4 | 150 | FOOT | $13.00 | $108.35 | $12.50 | |
| 11 | 81100300 | CON AT ST 1 GALVS | 10 | FOOT | $22.00 | $106.92 | $20.40 | |
| 12 | 81100400 | CON AT ST 1 1/4 GALVS | 10 | FOOT | $30.00 | $133.65 | $28.00 | |
| 13 | 81702381 | EC C XLP 2-1C#1 1C#6G | 166 | FOOT | $23.00 | $53.46 | $22.00 | |
| 14 | 81702418 | EC C XLP 3-1C#6 1C#8G | 166 | FOOT | $16.00 | $58.81 | $15.00 |