D7 ASH BORER CONTROL 2022-1
- Let date
- Friday, November 5, 2021
- Contract
- 74A86 · job page
- District
- District 7
- County
- Fayette, Clay, Effingham
- Highway
- Limits
- Tree removal on I-57 from mile marker 134 to mile marker 158.
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Brewster Companies, Inc. Low bidder | $139,700 | ||
| 2 | J & M Highway Safety, LLC | $180,100 | +28.9% | |
| 3 | Nettle Creek Nursery, Inc. | $294,000 | +110.5% | |
| 4 | Scruggs Machinery Equipment Construction Commodity Co. | $390,280 | +179.4% | |
| 5 | CSD Environmental Services, Inc. | $846,120 | +505.7% | |
| 6 | Endrizzi Contracting, Inc | $865,000 | +519.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Brewster Compan… | #2 J & M Highway S… | #3 Nettle Creek Nu… | #4 Scruggs Machine… | #5 CSD Environment… | #6 Endrizzi Contra… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 20100110 | TREE REMOV 6-15 | 3,000 | UNIT | $21.00 | $28.35 | $40.00 | $57.75 | $120.50 | $135.00 | |
| 2 | 20100210 | TREE REMOV OVER 15 | 3,000 | UNIT | $23.40 | $28.35 | $48.00 | $65.01 | $160.15 | $145.00 | |
| 3 | 67100100 | MOBILIZATION | 1 | L SUM | $6,500.00 | $10,000.00 | $30,000.00 | $22,000.00 | $4,170.00 | $25,000.00 |