D7 BRIDGE REPAIRS 2021-2
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Sangamo Construction Company Low bidder | $191,537 | ||
| 2 | Samron Midwest Contracting, Inc. | $208,478 | +8.8% | |
| 3 | MYS, Incorporated | $226,739 | +18.4% | |
| 4 | Plocher Construction Company, Inc. | $228,111 | +19.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Sangamo Constru… | #2 Samron Midwest … | #3 MYS, Incorporat… | #4 Plocher Constru… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X4401198 | HMA SURF REM VAR DP | 446.3 | SQ YD | $16.91 | $12.00 | $45.00 | $21.00 | |
| 2 | X7011800 | TRAF CONT-PROT BLR 21 | 1 | L SUM | $4,191.68 | $6,500.00 | $15,000.00 | $18,500.00 | |
| 3 | Z0001800 | APPROACH SL REP (PD) | 11 | SQ YD | $1,088.57 | $1,150.00 | $650.00 | $750.00 | |
| 4 | Z0012110 | BRD FLYASH/SLAG 2 1/4 | 153 | SQ YD | $185.29 | $350.00 | $250.00 | $275.00 | |
| 5 | Z0012130 | BR DECK SCAR 3/4 | 153 | SQ YD | $199.55 | $240.00 | $200.00 | $180.00 | |
| 6 | Z0016001 | DECK SLAB REP (FD-T1) | 3 | SQ YD | $2,115.63 | $1,750.00 | $2,500.00 | $2,250.00 | |
| 7 | Z0016002 | DECK SLAB REP (FD-T2) | 11 | SQ YD | $1,498.70 | $1,500.00 | $1,800.00 | $1,460.00 | |
| 8 | Z0016702 | DETOUR SIGNING | 1 | L SUM | $23,246.54 | $7,400.00 | $15,000.00 | $23,000.00 | |
| 9 | Z0041895 | POLYMER CONCRETE | 3.8 | CU FT | $1,126.16 | $1,050.00 | $1,500.00 | $1,250.00 | |
| 10 | 40600290 | BIT MATLS TACK CT | 201 | POUND | $5.19 | $5.50 | $3.00 | $5.00 | |
| 11 | 40604052 | HMA SC IL-9.5 C N70 | 37 | TON | $319.30 | $475.00 | $450.00 | $300.00 | |
| 12 | 48101200 | AGGREGATE SHLDS B | 3.5 | TON | $231.49 | $45.00 | $200.00 | $134.00 | |
| 13 | 50300260 | BR DECK GROOVING | 145 | SQ YD | $32.30 | $45.00 | $50.00 | $52.00 | |
| 14 | 60260100 | INLETS ADJUST | 1 | EACH | $4,365.04 | $875.00 | $1,250.00 | $432.00 | |
| 15 | 64200108 | SHOULDER RUM STRIP 8 | 122 | FOOT | $50.86 | $45.00 | $50.00 | $110.00 | |
| 16 | 67000400 | ENGR FIELD OFFICE A | 3 | CAL MO | $2,044.53 | $1,500.00 | $2,000.00 | $4,000.00 | |
| 17 | 67100100 | MOBILIZATION | 1 | L SUM | $11,300.65 | $12,000.00 | $20,000.00 | $18,000.00 | |
| 18 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $975.31 | $8,500.00 | $2,500.00 | $750.00 | |
| 19 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $165.96 | $100.00 | $125.00 | $115.00 | |
| 20 | 70300220 | TEMP PVT MK LINE 4 | 517 | FOOT | $6.39 | $0.00 | $3.00 | $1.00 | |
| 21 | 78001110 | PAINT PVT MK LINE 4 | 517 | FOOT | $6.39 | $2.00 | $3.00 | $6.50 |