(26-3)RS-1
Bidders 1
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Howell Paving, Inc. Low bidder | $4,499,036 |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Howell Paving, … |
|---|---|---|---|---|---|---|
| 1 | X1700081 | CL A PATCH T2 16 SPL | 846 | SQ YD | $250.00 | |
| 2 | X1700082 | CL A PATCH T4 16 SPL | 361 | SQ YD | $245.00 | |
| 3 | X1700105 | CL A PATCH T3 16 SPL | 32 | SQ YD | $250.00 | |
| 4 | Z0034105 | MATL TRANSFER DEVICE | 10,104 | TON | $2.28 | |
| 5 | 40600290 | BIT MATLS TACK CT | 67,738 | POUND | $1.44 | |
| 6 | 40600372 | LNG JNT SLNT HALF WD | 33,830 | FOOT | $1.38 | |
| 7 | 40600990 | TEMPORARY RAMP | 36 | SQ YD | $30.78 | |
| 8 | 40604052 | HMA SC IL-9.5 C N70 | 6,756 | TON | $115.64 | |
| 9 | 40605034 | P SC SMA 12.5 E N80 | 10,104 | TON | $163.36 | |
| 10 | 44000157 | HMA SURF REM 2 | 150,527 | SQ YD | $5.12 | |
| 11 | 44213000 | PATCH REINFORCEMENT | 1,238 | SQ YD | $70.00 | |
| 12 | 44213200 | SAW CUTS | 6,757 | FOOT | $0.0100 | |
| 13 | 44213204 | TIE BARS 3/4 | 130 | EACH | $7.50 | |
| 14 | 48102100 | AGG WEDGE SHLD TYPE B | 643 | TON | $91.63 | |
| 15 | 64200116 | SHOULDER RUM STRIP 16 | 67,660 | FOOT | $0.2300 | |
| 16 | 67000400 | ENGR FIELD OFFICE A | 2 | CAL MO | $6,177.05 | |
| 17 | 67100100 | MOBILIZATION | 1 | L SUM | $290,050.91 | |
| 18 | 70100420 | TRAF CONT-PROT 701411 | 4 | EACH | $650.00 | |
| 19 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $180,627.82 | |
| 20 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $150.00 | |
| 21 | 70300100 | SHORT TERM PAVT MKING | 34,428 | FOOT | $0.5900 | |
| 22 | 70300150 | SHRT TRM PAVT MK REM | 11,476 | SQ FT | $0.0100 | |
| 23 | 78000400 | THPL PVT MK LINE 6 | 67,660 | FOOT | $1.05 | |
| 24 | 78004230 | PREF PL PM TB INL L6 | 8,458 | FOOT | $5.50 | |
| 25 | 78011035 | GRV RCSD PVT MRKG 7 | 8,458 | FOOT | $1.69 | |
| 26 | 78100100 | RAISED REFL PAVT MKR | 422 | EACH | $37.59 | |
| 27 | 78300200 | RAISED REF PVT MK REM | 422 | EACH | $0.0100 |