(CF-X,D-X)RS-2
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Howell Paving, Inc. Low bidder | $757,391 | ||
| 2 | Ne-Co Asphalt Co., Inc. | $759,590 | +0.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Howell Paving, … | #2 Ne-Co Asphalt C… |
|---|---|---|---|---|---|---|---|
| 1 | X0326440 | SURF REM VAR DP (SPL) | 2,157 | SQ YD | $4.30 | $3.00 | |
| 2 | X4060995 | TEMPORARY RAMP SPL | 285 | SQ YD | $14.66 | $28.00 | |
| 3 | 40200800 | AGG SURF CSE B | 20 | TON | $85.27 | $40.00 | |
| 4 | 40600290 | BIT MATLS TACK CT | 14,668 | POUND | $1.38 | $0.6500 | |
| 5 | 40600370 | LONG JOINT SEALANT | 8,326 | FOOT | $2.82 | $2.27 | |
| 6 | 40600990 | TEMPORARY RAMP | 32 | SQ YD | $26.72 | $15.00 | |
| 7 | 40602970 | HMA BC IL-9.5FG N70 | 2,130 | TON | $88.44 | $83.00 | |
| 8 | 40604052 | HMA SC IL-9.5 C N70 | 2,434 | TON | $88.44 | $83.00 | |
| 9 | 40800029 | BIT MATLS TACK CT | 971 | POUND | $1.39 | $0.6500 | |
| 10 | 40800050 | INCIDENTAL HMA SURF | 226 | TON | $143.71 | $140.00 | |
| 11 | 44000155 | HMA SURF REM 1 1/2 | 21,730 | SQ YD | $1.45 | $2.00 | |
| 12 | 44201785 | CL D PATCH T1 12 | 4 | SQ YD | $257.33 | $170.00 | |
| 13 | 44201789 | CL D PATCH T2 12 | 834 | SQ YD | $145.50 | $170.00 | |
| 14 | 48102100 | AGG WEDGE SHLD TYPE B | 1,430 | TON | $25.33 | $16.00 | |
| 15 | 64200108 | SHOULDER RUM STRIP 8 | 975 | FOOT | $6.62 | $5.81 | |
| 16 | 67000400 | ENGR FIELD OFFICE A | 4 | CAL MO | $2,952.58 | $2,400.00 | |
| 17 | 67100100 | MOBILIZATION | 1 | L SUM | $6,017.07 | $12,500.00 | |
| 18 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $3,455.56 | $15,500.00 | |
| 19 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $12,618.07 | $19,500.00 | |
| 20 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $0.00 | $400.00 | |
| 21 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $60.01 | $134.25 | |
| 22 | 70300100 | SHORT TERM PAVT MKING | 2,164 | FOOT | $1.47 | $1.50 | |
| 23 | 70300150 | SHRT TRM PAVT MK REM | 241 | SQ FT | $3.56 | $3.00 | |
| 24 | 70300211 | TEMP PVT MK LTR & SYM PAINT | 48 | SQ FT | $0.00 | $0.00 | |
| 25 | 70300221 | TEMP PVT MK LINE 4 - PAINT | 17,239 | FOOT | $0.00 | $0.00 | |
| 26 | 70300241 | TEMP PVT MK LINE 6 - PAINT | 155 | FOOT | $0.00 | $0.00 | |
| 27 | 70300281 | TEMP PVT MK LINE 24 - PAINT | 134 | FOOT | $0.00 | $0.00 | |
| 28 | 78000100 | THPL PVT MK LTR & SYM | 48 | SQ FT | $45.00 | $45.00 | |
| 29 | 78000650 | THPL PVT MK LINE 24 | 134 | FOOT | $50.00 | $50.00 | |
| 30 | 78001110 | PAINT PVT MK LINE 4 | 17,239 | FOOT | $0.2800 | $0.2800 | |
| 31 | 78001130 | PAINT PVT MK LINE 6 | 155 | FOOT | $0.4200 | $0.4200 | |
| 32 | 78011000 | GRV RCSD PM LTR & SYM | 48 | SQ FT | $20.25 | $20.25 | |
| 33 | 78011125 | GRV RCSD PVT MRKG 25 | 134 | FOOT | $25.20 | $25.20 | |
| 34 | 78100100 | RAISED REFL PAVT MKR | 101 | EACH | $54.83 | $54.83 | |
| 35 | 78300200 | RAISED REF PVT MK REM | 101 | EACH | $3.64 | $10.00 |