(106,107)PVMT PRSV
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Beniach Construction Company, Inc. and Pavement Maintenance Systems, LLC Low bidder | $706,720 | ||
| 2 | Microsurfacing Contractors, LLC, a Division of Byrne and Jones Holding Company | $797,422 | +12.8% | |
| 3 | A. C. Pavement Striping Co. | $821,003 | +16.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Beniach Constru… | #2 Microsurfacing … | #3 A. C. Pavement … |
|---|---|---|---|---|---|---|---|---|
| 1 | Z0033650 | LONG JOINT REPAIR | 3 | TON | $0.0100 | $198.09 | $400.00 | |
| 2 | Z0049799 | PROT RESET SURVEY MRK | 4 | EACH | $424.00 | $1,000.00 | $1,200.00 | |
| 3 | 40500063 | CAPE SEAL,TY 2,MIX C | 156,988 | SQ YD | $3.50 | $4.10 | $4.47 | |
| 4 | 67100100 | MOBILIZATION | 1 | L SUM | $36,000.00 | $45,000.00 | $15,000.00 | |
| 5 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $33,000.00 | $24,100.00 | $15,000.00 | |
| 6 | 70107025 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $99.00 | $60.00 | $65.00 | |
| 7 | 70300100 | SHORT TERM PAVT MKING | 13,252 | FOOT | $0.4300 | $0.3900 | $0.3900 | |
| 8 | 70300220 | TEMP PVT MK LINE 4 | 152,521 | FOOT | $0.1900 | $0.1700 | $0.1700 | |
| 9 | 78001110 | PAINT PVT MK LINE 4 | 152,521 | FOOT | $0.0900 | $0.0900 | $0.1100 | |
| 10 | 78100100 | RAISED REFL PAVT MKR | 804 | EACH | $30.00 | $27.74 | $27.74 | |
| 11 | 78300200 | RAISED REF PVT MK REM | 805 | EACH | $14.00 | $14.00 | $14.00 |