D7 HMA RESURF 2018-2
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Ne-Co Asphalt Co., Inc. Low bidder | $196,083 | ||
| 2 | Howell Paving, Inc. | $218,895 | +11.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Ne-Co Asphalt C… | #2 Howell Paving, … |
|---|---|---|---|---|---|---|---|
| 1 | X7015005 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $65.00 | $140.92 | |
| 2 | Z0049799 | PROT RESET SURVEY MRK | 1 | EACH | $950.00 | $803.66 | |
| 3 | 40600290 | BIT MATLS TACK CT | 6,239 | POUND | $0.0100 | $1.50 | |
| 4 | 40600990 | TEMPORARY RAMP | 53 | SQ YD | $5.00 | $9.12 | |
| 5 | 40603345 | HMA SC "D" N90 | 1,165 | TON | $80.00 | $72.88 | |
| 6 | 44000155 | HMA SURF REM 1 1/2 | 13,863 | SQ YD | $1.25 | $0.3800 | |
| 7 | 44201811 | CL D PATCH T1 14 | 28 | SQ YD | $115.00 | $142.13 | |
| 8 | 44201815 | CL D PATCH T2 14 | 182 | SQ YD | $115.00 | $141.90 | |
| 9 | 44201819 | CL D PATCH T3 14 | 40 | SQ YD | $115.00 | $142.01 | |
| 10 | 44201821 | CL D PATCH T4 14 | 280 | SQ YD | $100.00 | $141.88 | |
| 11 | 48102100 | AGG WEDGE SHLD TYPE B | 444 | TON | $20.00 | $32.83 | |
| 12 | 67100100 | MOBILIZATION | 1 | L SUM | $3,000.00 | $12,507.15 | |
| 13 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $500.00 | $2,009.04 | |
| 14 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $6,500.00 | $2,788.63 | |
| 15 | 70300100 | SHORT TERM PAVT MKING | 390 | FOOT | $1.00 | $1.39 | |
| 16 | 70300150 | SHRT TRM PAVT MK REM | 130 | SQ FT | $2.00 | $2.59 | |
| 17 | 78001110 | PAINT PVT MK LINE 4 | 9,810 | FOOT | $0.3000 | $0.3000 | |
| 18 | 78100100 | RAISED REFL PAVT MKR | 49 | EACH | $66.00 | $65.62 |