D7 GUARDRAIL IMPROVEMENTS 2018-2
- Let date
- Friday, June 15, 2018
- Contract
- 74853 · job page
- District
- District 7
- County
- Clark, Crawford, Jasper
- Highway
- Limits
- Replacing existing non-crashworthy traffic barrier end-sections and steel plate beam guardrail at various locations.
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Midwest Fence Corporation Low bidder | $1,444,046 | ||
| 2 | COLLINS & HERMANN, INC. | $2,107,402 | +45.9% | |
| 3 | Lovewell Fencing, Inc. | $2,282,935 | +58.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Midwest Fence C… | #2 COLLINS & HERMA… | #3 Lovewell Fencin… |
|---|---|---|---|---|---|---|---|---|
| 1 | X2501000 | SEEDING CL 2 SPL | 0.5 | ACRE | $5,300.00 | $4,060.52 | $5,000.00 | |
| 2 | X4811900 | AGGREGATE SHLDS SPL | 2,059 | TON | $41.00 | $85.20 | $135.00 | |
| 3 | X6310088 | TRAF BAR TERM T6A SPL | 7 | EACH | $3,850.00 | $4,116.71 | $4,000.00 | |
| 4 | X6311217 | TRAF BAR TERM T6B SPL | 3 | EACH | $3,250.00 | $5,810.08 | $4,000.00 | |
| 5 | X6330725 | SPBGR (SHORT RADIUS) | 12.5 | FOOT | $60.00 | $33.23 | $65.00 | |
| 6 | 542D0220 | P CUL CL D 1 15 | 60 | FOOT | $42.00 | $147.86 | $95.00 | |
| 7 | 542D0229 | P CUL CL D 1 24 | 300 | FOOT | $57.00 | $170.28 | $125.00 | |
| 8 | 54262715 | METAL FL END SEC 15" | 2 | EACH | $150.00 | $887.15 | $1,500.00 | |
| 9 | 54262724 | METAL FL END SEC 24" | 10 | EACH | $185.00 | $1,035.01 | $1,850.00 | |
| 10 | 63000001 | SPBGR TY A 6FT POSTS | 21,778.5 | FOOT | $22.00 | $26.42 | $28.00 | |
| 11 | 63000003 | SPBGR TY A 9FT POSTS | 4,275 | FOOT | $25.00 | $30.00 | $40.00 | |
| 12 | 63000007 | SPBGR TY B 6FT POSTS | 50 | FOOT | $35.00 | $34.80 | $45.00 | |
| 13 | 63100045 | TRAF BAR TERM T2 | 22 | EACH | $1,200.00 | $1,130.42 | $1,350.00 | |
| 14 | 63100085 | TRAF BAR TERM T6 | 57 | EACH | $3,000.00 | $3,664.82 | $3,500.00 | |
| 15 | 63100167 | TR BAR TRM T1 SPL TAN | 113 | EACH | $2,800.00 | $3,515.86 | $2,900.00 | |
| 16 | 63100169 | TR BAR TRM T1 SPL FLR | 9 | EACH | $2,400.00 | $2,559.52 | $2,800.00 | |
| 17 | 63200310 | GUARDRAIL REMOV | 30,637 | FOOT | $5.00 | $4.78 | $7.00 | |
| 18 | 67100100 | MOBILIZATION | 1 | L SUM | $15,000.00 | $301,229.85 | $309,000.00 | |
| 19 | 72501000 | TERMINAL MARKER - DA | 118 | EACH | $30.00 | $24.90 | $25.00 | |
| 20 | 78200005 | GRDRAIL REF TYPE A | 360 | EACH | $8.00 | $3.11 | $15.00 |