Bid tab 74809

Let Jan 19, 2018 · District 7 · Clark

‹ Jan 2018 results

D7 AGG SHLD 2018-2

Let date
Friday, January 19, 2018
Contract
74809 · job page
District
District 7
County
Clark
Highway
Limits
9 miles of aggregate shoulders on IL 49 at Westerfield.
Classification
·
Project number

Bidders 6

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Howell Paving, Inc. Low bidder $114,104
2 Beniach Construction Co., Inc. $114,247 +0.1%
3 Phoenix Corporation of the Quad Cities $128,579 +12.7%
4 Feutz Contractors, Inc. $143,039 +25.4%
5 Ne-Co Asphalt Co., Inc. $145,456 +27.5%
6 A. J. Walker Construction Company $174,823 +53.2%

Bid tab: unit prices 4 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Howell Paving, …#2 Beniach Constru…#3 Phoenix Corpora…#4 Feutz Contracto…#5 Ne-Co Asphalt C…#6 A. J. Walker Co…
1X7015005 CHANGEABLE MESSAGE SN28CAL DA $104.17 $130.00 $60.00 $70.00 $75.00 $150.00
248102100 AGG WEDGE SHLD TYPE B4,828TON $21.31 $19.55 $20.50 $24.25 $27.00 $29.00
367100100 MOBILIZATION1L SUM $3,225.42 $6,800.00 $21,000.00 $6,000.00 $2,500.00 $7,065.75
470100460 TRAF CONT-PROT 7013061L SUM $5,077.06 $9,420.00 $6,925.00 $18,000.00 $10,500.00 $23,544.99