D7 AGG SHLD 2018-2
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Howell Paving, Inc. Low bidder | $114,104 | ||
| 2 | Beniach Construction Co., Inc. | $114,247 | +0.1% | |
| 3 | Phoenix Corporation of the Quad Cities | $128,579 | +12.7% | |
| 4 | Feutz Contractors, Inc. | $143,039 | +25.4% | |
| 5 | Ne-Co Asphalt Co., Inc. | $145,456 | +27.5% | |
| 6 | A. J. Walker Construction Company | $174,823 | +53.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Howell Paving, … | #2 Beniach Constru… | #3 Phoenix Corpora… | #4 Feutz Contracto… | #5 Ne-Co Asphalt C… | #6 A. J. Walker Co… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X7015005 | CHANGEABLE MESSAGE SN | 28 | CAL DA | $104.17 | $130.00 | $60.00 | $70.00 | $75.00 | $150.00 | |
| 2 | 48102100 | AGG WEDGE SHLD TYPE B | 4,828 | TON | $21.31 | $19.55 | $20.50 | $24.25 | $27.00 | $29.00 | |
| 3 | 67100100 | MOBILIZATION | 1 | L SUM | $3,225.42 | $6,800.00 | $21,000.00 | $6,000.00 | $2,500.00 | $7,065.75 | |
| 4 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $5,077.06 | $9,420.00 | $6,925.00 | $18,000.00 | $10,500.00 | $23,544.99 |