Bid tab 74808

Let Jan 19, 2018 · District 7 · Effingham, Clay

‹ Jan 2018 results

D7 AGG SHLD 2018-1

Let date
Friday, January 19, 2018
Contract
74808 · job page
District
District 7
County
Effingham, Clay
Highway
Limits
12.9 miles of aggregate shoulders on Dieterrich/Clay City Road.
Classification
·
Project number

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Howell Paving, Inc. Low bidder $212,290
2 Phoenix Corporation of the Quad Cities $222,221 +4.7%
3 Beniach Construction Co., Inc. $225,138 +6.1%
4 A. J. Walker Construction Company $325,647 +53.4%

Bid tab: unit prices 4 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Howell Paving, …#2 Phoenix Corpora…#3 Beniach Constru…#4 A. J. Walker Co…
1X7015005 CHANGEABLE MESSAGE SN28CAL DA $104.69 $55.00 $123.00 $150.00
248102100 AGG WEDGE SHLD TYPE B8,763TON $22.66 $20.94 $22.05 $31.20
367100100 MOBILIZATION1L SUM $3,302.44 $32,684.00 $13,500.00 $9,340.75
470100460 TRAF CONT-PROT 7013061L SUM $7,487.07 $4,499.78 $14,970.00 $38,700.29