12-51 I
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Phoenix Corporation of the Quad Cities Low bidder | $186,824 | ||
| 2 | A. J. Walker Construction Company | $245,351 | +31.3% | |
| 3 | CSD Environmental Services, Inc. | $269,090 | +44.0% | |
| 4 | Halverson Construction Co., Inc. | $287,322 | +53.8% | |
| 5 | Prado Construction | $364,415 | +95.1% | |
| 6 | Feutz Contractors, Inc. | $524,353 | +180.7% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Phoenix Corpora… | #2 A. J. Walker Co… | #3 CSD Environment… | #4 Halverson Const… | #5 Prado Construct… | #6 Feutz Contracto… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0100016 | CELL CONFINEMNT SYS | 2,698 | SQ YD | $18.30 | $21.42 | $20.21 | $25.00 | $26.92 | $31.54 | |
| 2 | X2110104 | TOPSOIL F & P 4 SPL | 2,698 | SQ YD | $5.10 | $15.05 | $7.23 | $24.00 | $13.92 | $21.00 | |
| 3 | X2501100 | SEEDING CL 3 SPL | 0.5 | ACRE | $3,825.00 | $5,520.00 | $4,581.60 | $3,350.00 | $10,166.93 | $3,700.00 | |
| 4 | X4402400 | CURB REMOVAL SPL | 239 | FOOT | $4.00 | $9.98 | $29.22 | $5.00 | $8.96 | $21.50 | |
| 5 | X5000015 | REM & REIN PIPE CULV | 8 | FOOT | $70.00 | $180.00 | $335.59 | $300.00 | $166.83 | $30.00 | |
| 6 | X6060505 | CONC CURB SPL | 239 | FOOT | $35.00 | $41.01 | $55.00 | $22.75 | $34.52 | $37.00 | |
| 7 | X6650206 | WOV W FENCE REM & RE | 86 | FOOT | $8.00 | $32.79 | $55.00 | $68.00 | $98.78 | $75.04 | |
| 8 | X7015005 | CHANGEABLE MESSAGE SN | 14 | CAL DA | $60.00 | $150.00 | $75.00 | $60.00 | $193.86 | $111.28 | |
| 9 | Z0018900 | DRILL-GROUT DOW BARS | 159 | EACH | $18.00 | $16.41 | $33.77 | $29.50 | $20.82 | $6.42 | |
| 10 | 20100110 | TREE REMOV 6-15 | 90 | UNIT | $40.00 | $29.73 | $37.03 | $70.00 | $32.59 | $97.00 | |
| 11 | 20201200 | REM & DISP UNS MATL | 570 | CU YD | $20.00 | $26.40 | $30.92 | $12.00 | $36.83 | $63.00 | |
| 12 | 20300100 | CHANNEL EXCAVATION | 140 | CU YD | $19.50 | $30.65 | $60.48 | $32.50 | $34.22 | $63.00 | |
| 13 | 20400800 | FURNISHED EXCAVATION | 1,395 | CU YD | $18.00 | $29.31 | $38.89 | $23.50 | $62.36 | $124.50 | |
| 14 | 25100630 | EROSION CONTR BLANKET | 2,698 | SQ YD | $1.90 | $1.89 | $2.20 | $1.60 | $1.68 | $1.75 | |
| 15 | 28000400 | PERIMETER EROS BAR | 149 | FOOT | $2.75 | $3.50 | $3.50 | $7.00 | $4.78 | $9.35 | |
| 16 | 28100207 | STONE RIPRAP CL A4 | 28 | TON | $82.00 | $58.31 | $133.55 | $144.00 | $95.82 | $150.00 | |
| 17 | 28100209 | STONE RIPRAP CL A5 | 169 | TON | $83.00 | $57.30 | $72.62 | $115.00 | $94.36 | $170.00 | |
| 18 | 28200200 | FILTER FABRIC | 154 | SQ YD | $1.00 | $3.00 | $7.31 | $2.50 | $4.68 | $1.10 | |
| 19 | 50104400 | CONC HDWL REM | 1 | EACH | $350.30 | $978.00 | $835.00 | $1,100.00 | $959.43 | $1,600.00 | |
| 20 | 50105220 | PIPE CULVERT REMOV | 8 | FOOT | $10.00 | $41.82 | $104.00 | $850.00 | $44.64 | $195.00 | |
| 21 | 54213681 | PRC FLAR END SEC 36 | 1 | EACH | $1,100.00 | $3,876.00 | $2,192.17 | $9,000.00 | $2,108.36 | $3,000.00 | |
| 22 | 54248510 | CONCRETE COLLAR | 0.5 | CU YD | $900.00 | $2,400.00 | $2,142.36 | $6,500.00 | $3,561.06 | $5,650.00 | |
| 23 | 63300575 | R&R RAIL ELEM EX GDRL | 300 | FOOT | $1.00 | $20.69 | $28.00 | $20.00 | $43.05 | $22.00 | |
| 24 | 67100100 | MOBILIZATION | 1 | L SUM | $30,990.05 | $7,000.00 | $25,267.50 | $17,000.00 | $19,650.67 | $30,000.00 | |
| 25 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $9,184.00 | $22,542.00 | $12,634.80 | $10,000.00 | $44,489.04 | $45,000.00 | |
| 26 | 70107007 | PAVT MK BLKOUT TAPE 7 | 40 | FOOT | $5.00 | $15.00 | $7.50 | $5.00 | $8.36 | $14.00 |