(68-3RA)PP
- Let date
- Friday, September 18, 2020
- Contract
- 72M40 · job page
- District
- District 6
- County
- Montgomery
- Highway
- Limits
- Patching on I-55 at the Coalfield Rest Area.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kinney Contractors, Inc. Low bidder | $181,367 | ||
| 2 | Prado Construction | $290,962 | +60.4% | |
| 3 | Beniach Construction Co., Inc. | $309,706 | +70.8% | |
| 4 | G. M. Sipes Construction, Inc. | $312,159 | +72.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kinney Contract… | #2 Prado Construct… | #3 Beniach Constru… | #4 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 44200050 | WELDED WIRE REINF | 1,148 | SQ YD | $12.00 | $10.60 | $19.00 | $5.00 | |
| 2 | 44200934 | CL B PATCH T2 8 | 470 | SQ YD | $115.00 | $168.92 | $185.00 | $190.00 | |
| 3 | 44200942 | CL B PATCH T3 8 | 136 | SQ YD | $113.00 | $178.30 | $168.00 | $190.00 | |
| 4 | 44200944 | CL B PATCH T4 8 | 708 | SQ YD | $106.00 | $164.94 | $164.00 | $185.00 | |
| 5 | 44201299 | DOWEL BARS 1 1/2 | 466 | EACH | $14.00 | $18.68 | $15.00 | $18.00 | |
| 6 | 44213200 | SAW CUTS | 6,357 | FOOT | $0.0100 | $3.08 | $0.0100 | $4.75 | |
| 7 | 44213204 | TIE BARS 3/4 | 843 | EACH | $12.50 | $14.20 | $10.00 | $5.00 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $4,000.00 | $9,241.80 | $15,000.00 | $12,500.00 | |
| 9 | 70100820 | TRAF CONT-PROT 701451 | 1 | L SUM | $2,000.00 | $8,877.16 | $31,500.00 | $5,000.00 |