(86-10)PP
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $623,502 | ||
| 2 | Kinney Contractors, Inc. | $702,748 | +12.7% | |
| 3 | Beniach Construction Co., Inc. | $752,213 | +20.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Kinney Contract… | #3 Beniach Constru… |
|---|---|---|---|---|---|---|---|---|
| 1 | 44200573 | CL A PATCH T1 12 | 360 | SQ YD | $265.00 | $300.00 | $389.00 | |
| 2 | 44200577 | CL A PATCH T2 12 | 726 | SQ YD | $215.00 | $225.00 | $238.00 | |
| 3 | 44200581 | CL A PATCH T3 12 | 255 | SQ YD | $215.00 | $223.00 | $234.00 | |
| 4 | 44200583 | CL A PATCH T4 12 | 782 | SQ YD | $205.00 | $221.00 | $232.00 | |
| 5 | 44213000 | PATCH REINFORCEMENT | 2,122 | SQ YD | $50.00 | $59.00 | $48.00 | |
| 6 | 44213200 | SAW CUTS | 11,190 | FOOT | $0.0100 | $1.50 | $0.0100 | |
| 7 | 44213204 | TIE BARS 3/4 | 427 | EACH | $5.00 | $14.00 | $9.00 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $31,000.00 | $20,000.00 | $37,000.00 | |
| 9 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $17,500.00 | $30,000.00 | $50,500.00 | |
| 10 | 70107025 | CHANGEABLE MESSAGE SN | 30 | CAL DA | $1.00 | $125.00 | $166.00 |