(59-1,2&68-1)CJS
- Let date
- Friday, January 17, 2020
- Contract
- 72L30 · job page
- District
- District 6
- County
- Macoupin, Montgomery
- Highway
- Limits
- 14.3 miles of crack and joint sealing on I-55 from the Madison County line to north of IL 16.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kinney Contractors, Inc. Low bidder | $167,695 | ||
| 2 | SKC Construction, Inc. | $183,495 | +9.4% | |
| 3 | Freehill Asphalt, Inc. | $221,443 | +32.1% | |
| 4 | Complete Asphalt Service Co. | $249,268 | +48.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kinney Contract… | #2 SKC Constructio… | #3 Freehill Asphal… | #4 Complete Asphal… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 45100100 | CRACK ROUTING (PAVT) | 7,846 | FOOT | $1.00 | $0.5000 | $0.1000 | $0.0100 | |
| 2 | 45100200 | CRACK FILLING | 28,545 | POUND | $3.30 | $3.37 | $3.86 | $7.98 | |
| 3 | 67100100 | MOBILIZATION | 1 | L SUM | $11,000.00 | $12,000.00 | $13,175.00 | $14,900.00 | |
| 4 | 70100420 | TRAF CONT-PROT 701411 | 14 | EACH | $300.00 | $1,500.00 | $100.00 | $100.00 | |
| 5 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $43,500.00 | $41,000.00 | $90,000.00 | $600.00 | |
| 6 | 70107025 | CHANGEABLE MESSAGE SN | 15 | CAL DA | $130.00 | $125.00 | $60.00 | $100.00 | |
| 7 | 70200100 | NIGHT WORK ZONE LIGHT | 1 | L SUM | $5,000.00 | $7,500.00 | $5,000.00 | $3,000.00 |