(4)RS-3, (101)RS-11
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Truman L. Flatt & Sons Co., Inc. Low bidder | $2,915,813 | ||
| 2 | P. H. Broughton & Sons, Inc. | $3,081,111 | +5.7% | |
| 3 | Illinois Valley Paving, a div of UCM, Inc. | $3,299,345 | +13.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Truman L. Flatt… | #2 P. H. Broughton… | #3 Illinois Valley… |
|---|---|---|---|---|---|---|---|---|
| 1 | X4401198 | HMA SURF REM VAR DP | 30,116 | SQ YD | $2.44 | $2.52 | $3.01 | |
| 2 | X4406255 | PART DEP REM T2 5.5 | 127 | SQ YD | $39.28 | $22.86 | $49.52 | |
| 3 | X4406455 | PART DEP REM T3 5.5 | 213 | SQ YD | $29.91 | $22.89 | $49.52 | |
| 4 | X4406655 | PART DEP REM T4 5.5 | 452 | SQ YD | $27.98 | $22.89 | $49.52 | |
| 5 | X4421000 | PARTIAL DEPTH PATCH | 244 | TON | $153.04 | $114.87 | $212.60 | |
| 6 | Z0033700 | LONG JOINT SEALANT | 31,522 | FOOT | $2.17 | $2.40 | $2.55 | |
| 7 | Z0034105 | MATL TRANSFER DEVICE | 7,421 | TON | $2.67 | $4.45 | $2.61 | |
| 8 | Z0038119 | PCC SUR REM 1 1/2 | 173 | SQ YD | $6.28 | $3.24 | $11.45 | |
| 9 | Z0076600 | TRAINEES | 2,000 | HOUR | $0.8000 | $0.8000 | $0.8000 | |
| 10 | Z0076604 | TRAINEES TPG | 2,000 | HOUR | $15.00 | $15.00 | $15.00 | |
| 11 | 21400100 | GRADING & SHAP DITCH | 3,269 | FOOT | $12.94 | $13.67 | $9.03 | |
| 12 | 25000200 | SEEDING CL 2 | 1.25 | ACRE | $1,522.50 | $2,894.66 | $1,575.00 | |
| 13 | 25000400 | NITROGEN FERT NUTR | 102 | POUND | $5.08 | $3.22 | $5.25 | |
| 14 | 25000500 | PHOSPHORUS FERT NUTR | 102 | POUND | $5.08 | $3.22 | $5.25 | |
| 15 | 25000600 | POTASSIUM FERT NUTR | 102 | POUND | $5.08 | $3.22 | $5.25 | |
| 16 | 25000700 | AGR GROUND LIMESTONE | 2.25 | TON | $812.00 | $187.62 | $840.00 | |
| 17 | 25100115 | MULCH METHOD 2 | 1.25 | ACRE | $1,218.00 | $2,894.66 | $1,260.00 | |
| 18 | 28000305 | TEMP DITCH CHECKS | 140 | FOOT | $23.35 | $24.66 | $40.09 | |
| 19 | 28000500 | INLET & PIPE PROTECT | 21 | EACH | $238.53 | $251.94 | $269.11 | |
| 20 | 40600290 | BIT MATLS TACK CT | 59,429 | POUND | $0.5100 | $0.5300 | $1.32 | |
| 21 | 40600982 | HMA SURF REM BUTT JT | 1,806 | SQ YD | $12.15 | $22.40 | $20.59 | |
| 22 | 40600985 | PCC SURF REM BUTT JT | 302 | SQ YD | $7.55 | $26.55 | $21.39 | |
| 23 | 40600990 | TEMPORARY RAMP | 206 | SQ YD | $13.12 | $27.02 | $10.57 | |
| 24 | 40603080 | HMA BC IL-19.0 N50 | 11,018 | TON | $78.56 | $78.44 | $83.84 | |
| 25 | 40604150 | P HMA SC IL-9.5 C N50 | 7,421 | TON | $96.07 | $91.44 | $101.62 | |
| 26 | 40800029 | BIT MATLS TACK CT | 1,847 | POUND | $0.6100 | $1.66 | $2.05 | |
| 27 | 40800050 | INCIDENTAL HMA SURF | 431 | TON | $226.13 | $172.23 | $184.05 | |
| 28 | 44000155 | HMA SURF REM 1 1/2 | 82,274 | SQ YD | $1.53 | $1.53 | $1.49 | |
| 29 | 44000160 | HMA SURF REM 2 3/4 | 5,621 | SQ YD | $3.07 | $2.06 | $3.60 | |
| 30 | 44004250 | PAVED SHLD REMOVAL | 687 | SQ YD | $16.85 | $36.82 | $28.91 | |
| 31 | 48102100 | AGG WEDGE SHLD TYPE B | 932 | TON | $39.59 | $41.81 | $24.15 | |
| 32 | 48203023 | HMA SHOULDERS 6 1/2 | 687 | SQ YD | $46.71 | $53.11 | $52.13 | |
| 33 | 48203100 | HMA SHOULDERS | 5,852 | TON | $76.15 | $84.22 | $97.90 | |
| 34 | 63000001 | SPBGR TY A 6FT POSTS | 1,271 | FOOT | $23.19 | $24.50 | $23.99 | |
| 35 | 63100167 | TR BAR TRM T1 SPL TAN | 8 | EACH | $3,009.48 | $2,889.30 | $3,113.25 | |
| 36 | 63200310 | GUARDRAIL REMOV | 1,471 | FOOT | $6.50 | $6.86 | $6.72 | |
| 37 | 64200108 | SHOULDER RUM STRIP 8 | 54,591 | FOOT | $0.2800 | $0.2900 | $0.3600 | |
| 38 | 67000400 | ENGR FIELD OFFICE A | 6 | CAL MO | $2,290.94 | $2,614.71 | $2,913.91 | |
| 39 | 67100100 | MOBILIZATION | 1 | L SUM | $14,682.72 | $63,448.19 | $14,635.69 | |
| 40 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $2,391.40 | $4,073.96 | $3,895.43 | |
| 41 | 70100460 | TRAF CONT-PROT 701306 | 1 | L SUM | $3,020.64 | $42,368.04 | $17,947.14 | |
| 42 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $9,501.97 | $3,001.86 | $3,654.15 | |
| 43 | 70300100 | SHORT TERM PAVT MKING | 11,565 | FOOT | $0.3800 | $0.6400 | $1.01 | |
| 44 | 70300150 | SHRT TRM PAVT MK REM | 1,285 | SQ FT | $2.90 | $2.68 | $3.95 | |
| 45 | 70300230 | TEMP PVT MK LINE 5 | 94,518 | FOOT | $0.00 | $0.0100 | $0.0100 | |
| 46 | 72501000 | TERMINAL MARKER - DA | 8 | EACH | $40.60 | $42.88 | $42.00 | |
| 47 | 78009005 | MOD URETH PM LINE 5 | 94,518 | FOOT | $0.5500 | $0.8500 | $0.8300 | |
| 48 | 78100100 | RAISED REFL PAVT MKR | 395 | EACH | $27.85 | $34.84 | $34.13 | |
| 49 | 78200005 | GRDRAIL REF TYPE A | 17 | EACH | $9.14 | $9.65 | $9.45 | |
| 50 | 78300200 | RAISED REF PVT MK REM | 395 | EACH | $14.44 | $10.82 | $11.64 |