(10-33,33)PP
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Beniach Construction Co., Inc. Low bidder | $445,307 | ||
| 2 | ICC Group Inc. | $488,600 | +9.7% | |
| 3 | Kinney Contractors, Inc. | $507,559 | +14.0% | |
| 4 | G. M. Sipes Construction, Inc. | $602,364 | +35.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Beniach Constru… | #2 ICC Group Inc. | #3 Kinney Contract… | #4 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7200203 | DETOUR SIGNING | 1 | L SUM | $23,250.00 | $50,000.00 | $20,000.00 | $25,000.00 | |
| 2 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $2,500.00 | $4,000.00 | $4,000.00 | $2,000.00 | |
| 3 | 44200050 | WELDED WIRE REINF | 339 | SQ YD | $18.80 | $45.00 | $19.00 | $15.00 | |
| 4 | 44201031 | CL B PATCH T2 15 | 690 | SQ YD | $305.00 | $300.00 | $294.00 | $375.00 | |
| 5 | 44201035 | CL B PATCH T3 15 | 36 | SQ YD | $305.00 | $360.00 | $292.00 | $375.00 | |
| 6 | 44201037 | CL B PATCH T4 15 | 303 | SQ YD | $295.00 | $290.00 | $290.00 | $370.00 | |
| 7 | 44201299 | DOWEL BARS 1 1/2 | 1,616 | EACH | $17.00 | $25.00 | $26.00 | $25.00 | |
| 8 | 44213200 | SAW CUTS | 3,830 | FOOT | $0.0100 | $3.25 | $7.00 | $6.95 | |
| 9 | 44213204 | TIE BARS 3/4 | 70 | EACH | $10.00 | $15.00 | $20.00 | $20.00 | |
| 10 | 67100100 | MOBILIZATION | 1 | L SUM | $10,000.00 | $24,297.50 | $30,500.00 | $30,000.00 | |
| 11 | 70100420 | TRAF CONT-PROT 701411 | 8 | EACH | $832.00 | $1,500.00 | $1,600.00 | $2,750.00 | |
| 12 | 70100800 | TRAF CONT-PROT 701401 | 1 | L SUM | $28,000.00 | $17,600.00 | $30,000.00 | $50,000.00 | |
| 13 | 70100820 | TRAF CONT-PROT 701451 | 1 | L SUM | $24,000.00 | $1,200.00 | $25,000.00 | $5,000.00 | |
| 14 | 70107025 | CHANGEABLE MESSAGE SN | 42 | CAL DA | $131.00 | $60.00 | $175.00 | $250.00 |