| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Kinney Contractors, Inc. Low bidder | $228,287 | ||
| 2 | Duce Construction Company | $236,954 | +3.8% | |
| 3 | Feutz Contractors, Inc. | $239,820 | +5.1% | |
| 4 | G. M. Sipes Construction, Inc. | $254,655 | +11.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Kinney Contract… | #2 Duce Constructi… | #3 Feutz Contracto… | #4 G. M. Sipes Con… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 44200050 | WELDED WIRE REINF | 594 | SQ YD | $14.00 | $18.00 | $20.00 | $10.00 | |
| 2 | 44200994 | CL B PATCH T2 12 | 164 | SQ YD | $190.00 | $176.00 | $190.00 | $275.00 | |
| 3 | 44200998 | CL B PATCH T3 12 | 41 | SQ YD | $187.00 | $159.00 | $186.00 | $275.00 | |
| 4 | 44201000 | CL B PATCH T4 12 | 409 | SQ YD | $184.00 | $151.00 | $180.00 | $250.00 | |
| 5 | 44201063 | CL B PATCH T2 18 | 35 | SQ YD | $265.00 | $207.00 | $230.00 | $295.00 | |
| 6 | 44201067 | CL B PATCH T3 18 | 35 | SQ YD | $264.00 | $204.00 | $225.00 | $295.00 | |
| 7 | 44201069 | CL B PATCH T4 18 | 110 | SQ YD | $263.00 | $180.00 | $220.00 | $270.00 | |
| 8 | 44201299 | DOWEL BARS 1 1/2 | 899 | EACH | $23.00 | $23.00 | $15.00 | $8.00 | |
| 9 | 44213200 | SAW CUTS | 2,390 | FOOT | $3.00 | $10.00 | $3.35 | $0.0100 | |
| 10 | 44213204 | TIE BARS 3/4 | 131 | EACH | $16.00 | $18.00 | $7.00 | $4.00 | |
| 11 | 67100100 | MOBILIZATION | 1 | L SUM | $12,000.00 | $14,000.00 | $13,000.00 | $12,000.00 | |
| 12 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $16,500.00 | $34,000.00 | $40,000.00 | $20,000.00 |