(28X-1, 29X-1)HSIP22-2
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Cross Construction, Inc. Low bidder | $1,441,144 | ||
| 2 | Open Road Paving Company LLC | $1,501,473 | +4.2% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Cross Construct… | #2 Open Road Pavin… |
|---|---|---|---|---|---|---|---|
| 1 | X4400196 | HMA SURF REM SPL | 532 | SQ YD | $20.00 | $16.00 | |
| 2 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $17,500.00 | $3,200.00 | |
| 3 | Z0070100 | SURV MONUMENT COV ASY | 2 | EACH | $1,400.00 | $1,062.55 | |
| 4 | 20200100 | EARTH EXCAVATION | 3,100 | CU YD | $65.00 | $48.00 | |
| 5 | 40600290 | BIT MATLS TACK CT | 5,271 | POUND | $1.20 | $2.65 | |
| 6 | 40800029 | BIT MATLS TACK CT | 240 | POUND | $8.00 | $7.85 | |
| 7 | 40800050 | INCIDENTAL HMA SURF | 46 | TON | $550.00 | $525.00 | |
| 8 | 44000100 | PAVEMENT REM | 581 | SQ YD | $82.00 | $30.00 | |
| 9 | 48102100 | AGG WEDGE SHLD TYPE B | 4 | TON | $500.00 | $492.50 | |
| 10 | 48203029 | HMA SHOULDERS 8 | 15,443 | SQ YD | $58.00 | $62.00 | |
| 11 | 64200108 | SHOULDER RUM STRIP 8 | 35,842 | FOOT | $0.3000 | $0.1700 | |
| 12 | 66900200 | NON SPL WASTE DISPOSL | 1,250 | CU YD | $75.00 | $79.58 | |
| 13 | 66900530 | SOIL DISPOSAL ANALY | 4 | EACH | $1,200.00 | $1,050.00 | |
| 14 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,530.00 | $2,200.00 | |
| 15 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,590.00 | $2,200.00 | |
| 16 | 66901006 | REG SUB MON | 2 | CAL DA | $3,700.00 | $1,100.00 | |
| 17 | 67100100 | MOBILIZATION | 1 | L SUM | $70,000.00 | $85,000.00 | |
| 18 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $38,000.00 | $120,600.00 |