LEROY,TOWANDA,BLOOM IMP 2024-2
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | H. J. Eppel & Co. Low bidder | $255,057 | ||
| 2 | Stark Excavating, Inc. | $311,536 | +22.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 H. J. Eppel & C… | #2 Stark Excavatin… |
|---|---|---|---|---|---|---|---|
| 1 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $3,000.00 | $6,500.00 | |
| 2 | 20200100 | EARTH EXCAVATION | 421 | CU YD | $40.00 | $80.00 | |
| 3 | 44000100 | PAVEMENT REM | 457 | SQ YD | $25.00 | $18.00 | |
| 4 | 50300225 | CONC STRUCT | 196.2 | CU YD | $785.00 | $925.00 | |
| 5 | 50800205 | REINF BARS, EPOXY CTD | 10,250 | POUND | $2.50 | $2.50 | |
| 6 | 66900200 | NON SPL WASTE DISPOSL | 168 | CU YD | $95.00 | $90.00 | |
| 7 | 66900530 | SOIL DISPOSAL ANALY | 3 | EACH | $1,250.00 | $1,300.00 | |
| 8 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,000.00 | $6,100.00 | |
| 9 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,000.00 | $6,100.00 | |
| 10 | 66901006 | REG SUB MON | 6 | CAL DA | $990.00 | $1,050.00 | |
| 11 | 67100100 | MOBILIZATION | 1 | L SUM | $14,500.00 | $18,500.00 |