CLINTON/MONTICELLO IMP 2022-1
- Let date
- Friday, April 29, 2022
- Contract
- 70F45 · job page
- District
- District 5
- County
- Dewitt, Piatt
- Highway
- Limits
- 884.93 ft/ 0.168 miles of Patching and Parking Improvements at the Clinton and Monticello Complex with Drainage Improvements.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Illiana Construction Co., Inc., A Div. of Champaign Asphalt Company Low bidder | $626,070 | ||
| 2 | Otto Baum Company, Inc. | $850,916 | +35.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Illiana Constru… | #2 Otto Baum Compa… |
|---|---|---|---|---|---|---|---|
| 1 | X0300010 | BIT MATLS FS | 5,855 | POUND | $1.40 | $1.43 | |
| 2 | X1500005 | BIT SURF TREATMNT A2 | 13,011 | SQ YD | $8.50 | $7.97 | |
| 3 | X6061460 | PAVED DITCH SPEC | 336 | FOOT | $120.00 | $105.42 | |
| 4 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $6,000.00 | $7,525.70 | |
| 5 | 20200100 | EARTH EXCAVATION | 1,200 | CU YD | $46.00 | $84.69 | |
| 6 | 28100805 | STONE DUMP RIP CL A3 | 4 | TON | $740.00 | $1,377.09 | |
| 7 | 28200200 | FILTER FABRIC | 6 | SQ YD | $49.00 | $502.13 | |
| 8 | 35100500 | AGG BASE CSE A 6 | 3,551 | SQ YD | $21.00 | $27.70 | |
| 9 | 35100700 | AGG BASE CSE A 8 | 920 | SQ YD | $29.00 | $56.37 | |
| 10 | 40600275 | BIT MATLS PR CT | 7,983 | POUND | $1.38 | $1.77 | |
| 11 | 40600290 | BIT MATLS TACK CT | 802 | POUND | $1.25 | $1.60 | |
| 12 | 40603230 | P HMA BC IL19.0 N50 | 500 | TON | $247.10 | $317.24 | |
| 13 | 40604150 | P HMA SC IL-9.5 C N50 | 301 | TON | $344.80 | $442.67 | |
| 14 | 44004000 | PAVED DITCH REMOVAL | 57 | FOOT | $14.00 | $143.82 | |
| 15 | 50105220 | PIPE CULVERT REMOV | 31 | FOOT | $27.00 | $109.53 | |
| 16 | 542A0217 | P CUL CL A 1 12 | 110 | FOOT | $120.00 | $214.66 | |
| 17 | 54213657 | PRC FLAR END SEC 12 | 1 | EACH | $1,650.00 | $2,042.06 | |
| 18 | 60236200 | INLETS TA T8G | 1 | EACH | $3,090.00 | $5,293.06 | |
| 19 | 60500060 | REMOV INLETS | 1 | EACH | $330.00 | $3,395.40 | |
| 20 | 66900200 | NON SPL WASTE DISPOSL | 92 | CU YD | $54.30 | $180.66 | |
| 21 | 66900530 | SOIL DISPOSAL ANALY | 2 | EACH | $1,050.00 | $2,125.00 | |
| 22 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,200.00 | $3,187.50 | |
| 23 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,200.00 | $2,975.00 | |
| 24 | 66901006 | REG SUB MON | 5 | CAL DA | $1,100.00 | $2,018.75 | |
| 25 | 67100100 | MOBILIZATION | 1 | L SUM | $25,000.00 | $45,186.11 |