54BR-2
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Stark Excavating, Inc. Low bidder | $434,660 | ||
| 2 | White Construction LLC | $523,818 | +20.5% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Stark Excavatin… | #2 White Construct… |
|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $4,500.00 | $10,000.00 | |
| 2 | Z0012754 | STR REP CON DP = < 5 | 16 | SQ FT | $365.00 | $400.00 | |
| 3 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $1,500.00 | $20,000.00 | |
| 4 | 20400800 | FURNISHED EXCAVATION | 50 | CU YD | $200.00 | $200.00 | |
| 5 | 25000210 | SEEDING CL 2A | 0.25 | ACRE | $9,250.00 | $8,800.00 | |
| 6 | 25000400 | NITROGEN FERT NUTR | 22.5 | POUND | $1.60 | $1.60 | |
| 7 | 25000500 | PHOSPHORUS FERT NUTR | 22.5 | POUND | $1.60 | $1.60 | |
| 8 | 25000600 | POTASSIUM FERT NUTR | 22.5 | POUND | $1.60 | $1.60 | |
| 9 | 25100630 | EROSION CONTR BLANKET | 478 | SQ YD | $2.60 | $2.50 | |
| 10 | 28000250 | TEMP EROS CONTR SEED | 50 | POUND | $4.25 | $20.00 | |
| 11 | 40604050 | HMA SC IL-9.5 C N50 | 14.1 | TON | $1,025.00 | $1,000.00 | |
| 12 | 48102100 | AGG WEDGE SHLD TYPE B | 56 | TON | $125.00 | $110.00 | |
| 13 | 50101500 | REM EXIST SUP-STR | 1 | EACH | $20,000.00 | $74,000.00 | |
| 14 | 50102400 | CONC REM | 0.4 | CU YD | $12,000.00 | $10,000.00 | |
| 15 | 50104000 | BRIDGE RAIL REMOVAL | 101 | FOOT | $25.00 | $50.00 | |
| 16 | 50300225 | CONC STRUCT | 0.4 | CU YD | $10,750.00 | $10,000.00 | |
| 17 | 50400405 | P P CONC DK BM 21 DP | 1,460 | SQ FT | $128.00 | $125.00 | |
| 18 | 50800205 | REINF BARS, EPOXY CTD | 30 | POUND | $28.00 | $70.00 | |
| 19 | 50900211 | STEEL RAILING TY IL-OH | 117 | FOOT | $650.00 | $618.85 | |
| 20 | 51500100 | NAME PLATES | 1 | EACH | $750.00 | $750.00 | |
| 21 | 58100200 | WATERPRF MEMBRANE SYS | 164 | SQ YD | $135.00 | $160.00 | |
| 22 | 58300100 | PC MORTAR FAIRING CSE | 438 | FOOT | $3.00 | $15.00 | |
| 23 | 63000003 | SPBGR TY A 9FT POSTS | 150 | FOOT | $42.00 | $41.05 | |
| 24 | 63100117 | TRAF BAR TERM T13 | 4 | EACH | $4,400.00 | $4,245.00 | |
| 25 | 63100167 | TR BAR TRM T1 SPL TAN | 4 | EACH | $3,750.00 | $3,620.00 | |
| 26 | 63200310 | GUARDRAIL REMOV | 513 | FOOT | $6.75 | $13.95 | |
| 27 | 67100100 | MOBILIZATION | 1 | L SUM | $25,250.00 | $30,000.00 | |
| 28 | 72501000 | TERMINAL MARKER - DA | 4 | EACH | $50.00 | $47.50 | |
| 29 | 78200005 | GRDRAIL REF TYPE A | 8 | EACH | $10.00 | $9.50 |