D4 PARKING LOT RESURF 2023
Bidders 6
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Gensini Excavating, Inc. Low bidder | $316,237 | ||
| 2 | Knapp Concrete Contractors, Inc. | $400,058 | +26.5% | |
| 3 | Illinois Civil Contractors, Inc. | $427,714 | +35.3% | |
| 4 | R. A. Cullinan and Son, a div of UCM, Inc. | $455,359 | +44.0% | |
| 5 | McCarthy Improvement Company | $576,160 | +82.2% | |
| 6 | Otto Baum Company, Inc. | $598,715 | +89.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Gensini Excavat… | #2 Knapp Concrete … | #3 Illinois Civil … | #4 R. A. Cullinan … | #5 McCarthy Improv… | #6 Otto Baum Compa… |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | X0350810 | BOLLARD REMOVAL | 12 | EACH | $150.00 | $350.00 | $230.57 | $151.72 | $350.00 | $531.41 | |
| 2 | Z0001110 | GAS VALVE ADJUSTED | 1 | EACH | $350.00 | $4,200.00 | $182.22 | $2,332.45 | $500.00 | $1,113.41 | |
| 3 | Z0004002 | BOLLARDS | 12 | EACH | $1,500.00 | $820.00 | $700.11 | $875.45 | $900.00 | $1,169.08 | |
| 4 | Z0013798 | CONSTRUCTION LAYOUT | 1 | L SUM | $10,000.00 | $10,000.00 | $10,533.70 | $8,613.92 | $14,800.00 | $8,823.74 | |
| 5 | 20200100 | EARTH EXCAVATION | 828 | CU YD | $20.00 | $47.00 | $68.16 | $56.79 | $45.00 | $142.16 | |
| 6 | 28000400 | PERIMETER EROS BAR | 200 | FOOT | $4.00 | $7.00 | $6.42 | $19.78 | $5.00 | $22.38 | |
| 7 | 42000301 | PCC PVT 8 JOINTED | 3,469 | SQ YD | $71.50 | $83.00 | $86.68 | $95.57 | $130.00 | $90.78 | |
| 8 | 42001300 | PROTECTIVE COAT | 3,469 | SQ YD | $1.50 | $3.00 | $0.5500 | $2.00 | $1.60 | $2.86 | |
| 9 | 44000100 | PAVEMENT REM | 749 | SQ YD | $10.00 | $32.00 | $24.28 | $22.43 | $20.00 | $112.58 | |
| 10 | 60260300 | INLETS ADJ NEW T1F OL | 1 | EACH | $500.00 | $1,200.00 | $1,659.58 | $3,041.07 | $2,100.00 | $3,939.55 | |
| 11 | 67100100 | MOBILIZATION | 1 | L SUM | $7,500.00 | $8,000.00 | $25,662.81 | $22,796.68 | $34,000.00 | $33,088.55 |