- Highway
- Limits
- This project is 0.26 miles in length. It is located at the structure carrying IL 41 over KJRY Railway and BNSF Railway (SN 055-0008), 2.8 miles South of Bushnell. Work includes bridge repair (structural repairs) and shoulder repair.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | County Contractors, Inc. Low bidder | $110,055 | ||
| 2 | Brandt Construction Co. | $162,952 | +48.1% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 County Contract… | #2 Brandt Construc… |
|---|---|---|---|---|---|---|---|
| 1 | X0326444 | SURFACE FILLER SPL | 2 | GALLON | $2,450.00 | $2,655.00 | |
| 2 | X5030550 | PROTECTIVE COAT SPL | 484 | SQ YD | $20.00 | $75.50 | |
| 3 | X6062700 | CONC GUTTER TA SPL | 20 | FOOT | $145.00 | $320.00 | |
| 4 | Z0001002 | GDRL AGG EROS CONT | 263 | TON | $110.00 | $125.00 | |
| 5 | Z0012754 | STR REP CON DP = < 5 | 19 | SQ FT | $350.00 | $510.00 | |
| 6 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $12,000.00 | $25,000.00 | |
| 7 | 20200100 | EARTH EXCAVATION | 29 | CU YD | $300.00 | $50.00 | |
| 8 | 28100825 | STONE DUMP RIP CL B3 | 30 | TON | $115.00 | $150.00 | |
| 9 | 44000400 | GUTTER REM | 20 | FOOT | $45.00 | $75.00 | |
| 10 | 44004250 | PAVED SHLD REMOVAL | 15 | SQ YD | $165.00 | $165.00 | |
| 11 | 48300800 | PCC SHOULDERS 13 | 15 | SQ YD | $300.00 | $350.00 | |
| 12 | 59000200 | EPOXY CRACK INJECTION | 22 | FOOT | $100.00 | $280.00 | |
| 13 | 60260100 | INLETS ADJUST | 2 | EACH | $1,150.00 | $2,200.00 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $13,500.00 | $9,000.00 | |
| 15 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $4,500.00 | $10,000.00 | |
| 16 | 70103815 | TR CONT SURVEILLANCE | 2 | CAL DA | $150.00 | $500.00 | |
| 17 | 70107025 | CHANGEABLE MESSAGE SN | 14 | CAL DA | $155.00 | $100.00 |