(37-24)CLV
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Phoenix Corporation of the Quad Cities Low bidder | $79,729 | ||
| 2 | Lee Hood d/b/a Hood Demolition & Excavation | $104,452 | +31.0% | |
| 3 | Valley Construction Co. | $123,457 | +54.8% | |
| 4 | Brandt Construction Co. | $136,000 | +70.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Phoenix Corpora… | #2 Lee Hood d/b/a … | #3 Valley Construc… | #4 Brandt Construc… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Z0010605 | CLEAN DRAINAGE SYSTEM | 1 | L SUM | $10,500.00 | $12,000.00 | $24,450.00 | $11,000.00 | |
| 2 | Z0022800 | FENCE REMOVAL | 40 | FOOT | $5.25 | $42.00 | $22.00 | $10.00 | |
| 3 | 28100807 | STONE DUMP RIP CL A4 | 119.6 | TON | $85.00 | $45.00 | $109.00 | $101.50 | |
| 4 | 44200050 | WELDED WIRE REINF | 470 | SQ YD | $22.00 | $25.00 | $37.00 | $25.00 | |
| 5 | 50300225 | CONC STRUCT | 54.4 | CU YD | $520.00 | $900.00 | $527.00 | $1,200.00 | |
| 6 | 66500105 | WOV W FENCE 4 | 40 | FOOT | $25.00 | $42.00 | $82.00 | $55.00 | |
| 7 | 67100100 | MOBILIZATION | 1 | L SUM | $5,500.00 | $10,000.00 | $4,500.00 | $8,230.60 | |
| 8 | 70100700 | TRAF CONT-PROT 701406 | 1 | L SUM | $13,725.00 | $13,000.00 | $31,251.58 | $25,000.00 |