Bid tab 66P24

Let Jun 14, 2024 · District 3 · Lasalle Sign up free

‹ Jun 2024 results

D3 CRACK SEALING 2025-02

Let date
Friday, June 14, 2024
Contract
66P24 · job page
District
District 3
County
Lasalle
Highway
Limits
14.45 miles of routing and crack sealing. Work begins in Ottawa at IL 23 and E Freemont Street on IL 23/IL71 including Columbus Street and LaSalle Street. Work continues at the intersection of Hitt Street and IL 23 to McKinley Rd. Work continues in Streator on IL 18, 0.1 miles east of IL 251 to east 0.1 miles West of E 16th Rd.

Bidders 4

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 Denler, Inc. Low bidder $88,496
2 SKC Construction, Inc. $146,430 +65.5%
3 Complete Asphalt Service Co. $157,395 +77.9%
4 Freehill Asphalt, Inc. $183,973 +107.9%

Bid tab: unit prices 6 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 Denler, Inc.#2 SKC Constructio…#3 Complete Asphal…#4 Freehill Asphal…
1X7010216 TRAF CONT & PROT SPL1L SUM $15,000.00 $16,000.00 $25,000.00 $40,000.00
2Z0030850 TEMP INFO SIGNING84SQ FT $30.00 $40.00 $40.00 $40.00
3Z0048665 RR PROT LIABILITY INS1L SUM $3,000.00 $6,500.00 $14,000.00 $7,200.00
445100100 CRACK ROUTING (PAVT)85,372FOOT $0.0100 $0.1000 $0.0100 $0.2000
545100200 CRACK FILLING32,869POUND $1.89 $2.80 $3.20 $3.22
667100100 MOBILIZATION1L SUM $5,000.00 $20,000.00 $9,000.00 $10,500.00