(915S)RS,MG
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Iroquois Paving Corporation Low bidder | $294,354 | ||
| 2 | Kankakee Valley Construction Company, Inc. | $303,783 | +3.2% | |
| 3 | Cross Construction, Inc. | $326,830 | +11.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Iroquois Paving… | #2 Kankakee Valley… | #3 Cross Construct… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0320050 | CONSTRUCTN LAYOUT SPL | 1 | L SUM | $3,700.00 | $4,000.00 | $5,900.00 | |
| 2 | X4400196 | HMA SURF REM SPL | 6,425 | SQ YD | $8.75 | $7.40 | $8.00 | |
| 3 | Z0003300 | BASE CSE REMOV SPL | 160 | SQ YD | $12.75 | $7.40 | $12.00 | |
| 4 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $37.00 | $35.00 | $70.00 | |
| 5 | 21001000 | GEOTECH FAB F/GR STAB | 25 | SQ YD | $11.65 | $2.40 | $73.00 | |
| 6 | 35800200 | AGG BASE REPAIR | 25 | TON | $40.00 | $65.00 | $170.00 | |
| 7 | 40600290 | BIT MATLS TACK CT | 1,482 | POUND | $0.0100 | $2.00 | $1.20 | |
| 8 | 40600906 | P HMA BC HM N70 | 10 | TON | $0.0100 | $265.00 | $410.00 | |
| 9 | 40600990 | TEMPORARY RAMP | 476 | SQ YD | $0.0100 | $8.75 | $22.00 | |
| 10 | 40603235 | P HMA BC IL19.0 N70 | 922 | TON | $140.00 | $137.00 | $150.00 | |
| 11 | 40604152 | P HMA SC IL-9.5 C N70 | 533 | TON | $150.00 | $182.00 | $165.00 | |
| 12 | 67100100 | MOBILIZATION | 1 | L SUM | $17,000.00 | $13,000.00 | $13,000.00 | |
| 13 | 70100450 | TRAF CONT-PROT 701201 | 1 | L SUM | $3,500.00 | $1,800.00 | $3,000.00 |