(110, 111)SFY
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Advanced Asphalt Company Low bidder | $1,512,236 | ||
| 2 | D. Construction, Inc. | $1,716,075 | +13.5% | |
| 3 | Kankakee Valley Construction Company, Inc. | $1,915,067 | +26.6% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Advanced Asphal… | #2 D. Construction… | #3 Kankakee Valley… |
|---|---|---|---|---|---|---|---|---|
| 1 | X0800001 | SHLDR REM SPL | 31,301 | SQ YD | $7.50 | $7.75 | $5.60 | |
| 2 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $27.50 | $25.00 | $25.00 | |
| 3 | 40600290 | BIT MATLS TACK CT | 14,100 | POUND | $0.8000 | $0.0100 | $0.0100 | |
| 4 | 40800050 | INCIDENTAL HMA SURF | 1.9 | TON | $250.00 | $300.00 | $1,100.00 | |
| 5 | 44000157 | HMA SURF REM 2 | 16 | SQ YD | $9.50 | $50.00 | $97.00 | |
| 6 | 48203029 | HMA SHOULDERS 8 | 31,301 | SQ YD | $34.00 | $40.00 | $51.25 | |
| 7 | 64200108 | SHOULDER RUM STRIP 8 | 69,915 | FOOT | $0.4000 | $0.5100 | $0.2500 | |
| 8 | 66900200 | NON SPL WASTE DISPOSL | 40 | CU YD | $115.00 | $100.00 | $124.00 | |
| 9 | 66900530 | SOIL DISPOSAL ANALY | 1 | EACH | $1,650.00 | $1,925.00 | $1,500.00 | |
| 10 | 66901001 | REG SUB P-CONST PLAN | 1 | L SUM | $2,865.00 | $2,200.00 | $2,600.00 | |
| 11 | 66901003 | REG SUB F CON REPORT | 1 | L SUM | $2,100.00 | $2,200.00 | $1,900.00 | |
| 12 | 66901006 | REG SUB MON | 1 | CAL DA | $980.00 | $1,045.00 | $890.00 | |
| 13 | 67100100 | MOBILIZATION | 1 | L SUM | $90,000.00 | $81,000.00 | $70,000.00 | |
| 14 | 70100500 | TRAF CONT-PROT 701326 | 1 | L SUM | $48,500.00 | $29,500.00 | $12,800.00 | |
| 15 | 70103815 | TR CONT SURVEILLANCE | 10 | CAL DA | $1.00 | $400.00 | $0.0100 | |
| 16 | 78001110 | PAINT PVT MK LINE 4 | 143,412 | FOOT | $0.1500 | $0.4000 | $0.1300 |