D3 IL 54 PP 2020-4
Bidders 3
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $285,429 | ||
| 2 | Beniach Construction Co., Inc. | $360,890 | +26.4% | |
| 3 | Kinney Contractors, Inc. | $413,577 | +44.9% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Beniach Constru… | #3 Kinney Contract… |
|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $5,000.00 | $7,800.00 | $40,000.00 | |
| 2 | Z0017099 | DOWEL BAR ASSEMBLY | 19 | EACH | $50.00 | $149.00 | $300.00 | |
| 3 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $1.00 | $30.00 | $40.00 | |
| 4 | 42000060 | WELDED WIRE REINF | 270 | SQ YD | $7.50 | $10.00 | $15.00 | |
| 5 | 44200956 | CL B PATCH T2 9 | 72 | SQ YD | $180.00 | $213.00 | $165.00 | |
| 6 | 44200962 | CL B PATCH T3 9 | 22 | SQ YD | $180.00 | $199.00 | $163.00 | |
| 7 | 44200964 | CL B PATCH T4 9 | 72 | SQ YD | $180.00 | $196.00 | $160.00 | |
| 8 | 44201007 | CL B PATCH T2 13 | 941 | SQ YD | $200.00 | $236.00 | $205.00 | |
| 9 | 44201011 | CL B PATCH T3 13 | 162 | SQ YD | $200.00 | $228.00 | $203.00 | |
| 10 | 44201013 | CL B PATCH T4 13 | 29 | SQ YD | $200.00 | $222.00 | $200.00 | |
| 11 | 44201299 | DOWEL BARS 1 1/2 | 2,180 | EACH | $5.00 | $12.70 | $25.00 | |
| 12 | 44213200 | SAW CUTS | 5,702 | FOOT | $0.0100 | $0.0100 | $5.00 | |
| 13 | 44213204 | TIE BARS 3/4 | 35 | EACH | $5.00 | $8.00 | $16.00 | |
| 14 | 67100100 | MOBILIZATION | 1 | L SUM | $10,000.00 | $19,000.00 | $20,000.00 |