D3 IL 38 PP 2020-2
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lorusso Cement Contractors, Inc. Low bidder | $149,997 | ||
| 2 | G. M. Sipes Construction, Inc. | $195,424 | +30.3% | |
| 3 | ERA-Valdivia Contractors, Inc. | $260,910 | +73.9% | |
| 4 | Alliance Contractors, Inc. | $280,523 | +87.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lorusso Cement … | #2 G. M. Sipes Con… | #3 ERA-Valdivia Co… | #4 Alliance Contra… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $3,000.00 | $5,000.00 | $8,500.00 | $3,250.00 | |
| 2 | Z0017099 | DOWEL BAR ASSEMBLY | 15 | EACH | $500.00 | $75.00 | $250.00 | $100.00 | |
| 3 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $21.00 | $1.00 | $25.00 | $24.00 | |
| 4 | 42000060 | WELDED WIRE REINF | 220 | SQ YD | $4.50 | $7.50 | $22.00 | $10.00 | |
| 5 | 44201007 | CL B PATCH T2 13 | 450 | SQ YD | $150.38 | $260.00 | $275.00 | $336.00 | |
| 6 | 44201011 | CL B PATCH T3 13 | 20 | SQ YD | $150.38 | $260.00 | $450.00 | $336.00 | |
| 7 | 44201013 | CL B PATCH T4 13 | 200 | SQ YD | $150.38 | $250.00 | $225.00 | $336.00 | |
| 8 | 44201299 | DOWEL BARS 1 1/2 | 1,200 | EACH | $11.04 | $5.00 | $26.00 | $10.00 | |
| 9 | 44213200 | SAW CUTS | 3,214 | FOOT | $5.85 | $0.0100 | $6.75 | $5.00 | |
| 10 | 44213204 | TIE BARS 3/4 | 75 | EACH | $10.94 | $5.00 | $35.00 | $5.00 | |
| 11 | 67100100 | MOBILIZATION | 1 | L SUM | $4,000.00 | $9,000.00 | $9,500.00 | $19,000.00 |