D3 IL 65 PP 2020-1
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | Lorusso Cement Contractors, Inc. Low bidder | $405,300 | ||
| 2 | G. M. Sipes Construction, Inc. | $476,680 | +17.6% | |
| 3 | Alliance Contractors, Inc. | $803,690 | +98.3% | |
| 4 | ERA-Valdivia Contractors, Inc. | $820,102 | +102.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 Lorusso Cement … | #2 G. M. Sipes Con… | #3 Alliance Contra… | #4 ERA-Valdivia Co… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | X7010216 | TRAF CONT & PROT SPL | 1 | L SUM | $4,562.25 | $5,000.00 | $4,250.00 | $16,000.00 | |
| 2 | Z0030850 | TEMP INFO SIGNING | 42 | SQ FT | $21.00 | $1.00 | $24.00 | $25.00 | |
| 3 | 42000060 | WELDED WIRE REINF | 1,036 | SQ YD | $4.50 | $7.50 | $10.00 | $22.00 | |
| 4 | 44200994 | CL B PATCH T2 12 | 313 | SQ YD | $138.10 | $215.00 | $325.00 | $275.00 | |
| 5 | 44200998 | CL B PATCH T3 12 | 300 | SQ YD | $138.10 | $205.00 | $325.00 | $275.00 | |
| 6 | 44201000 | CL B PATCH T4 12 | 501 | SQ YD | $138.10 | $195.00 | $325.00 | $275.00 | |
| 7 | 44201019 | CL B PATCH T2 14 | 702 | SQ YD | $154.41 | $225.00 | $331.00 | $325.00 | |
| 8 | 44201023 | CL B PATCH T3 14 | 128 | SQ YD | $154.41 | $215.00 | $331.00 | $350.00 | |
| 9 | 44201025 | CL B PATCH T4 14 | 107 | SQ YD | $154.41 | $205.00 | $331.00 | $350.00 | |
| 10 | 44201299 | DOWEL BARS 1 1/2 | 2,820 | EACH | $11.04 | $5.00 | $10.00 | $26.00 | |
| 11 | 44213200 | SAW CUTS | 7,844 | FOOT | $6.14 | $0.0100 | $5.00 | $7.10 | |
| 12 | 44213204 | TIE BARS 3/4 | 159 | EACH | $49.52 | $5.00 | $5.00 | $22.00 | |
| 13 | 67100100 | MOBILIZATION | 1 | L SUM | $9,500.00 | $15,000.00 | $47,660.00 | $31,000.00 |