D2 PP 2022-3
- Let date
- Friday, November 5, 2021
- Contract
- 64R28 · job page
- District
- District 2
- County
- Rock Island
- Highway
- Limits
- Pavement patching from Kennedy Dr in East Moline to Hospital RD in Silvis.
Bidders 4
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $637,757 | ||
| 2 | Kinney Contractors, Inc. | $648,084 | +1.6% | |
| 3 | Brandt Construction Co. | $823,114 | +29.1% | |
| 4 | Valley Construction Co. | $873,842 | +37.0% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Kinney Contract… | #3 Brandt Construc… | #4 Valley Construc… |
|---|---|---|---|---|---|---|---|---|---|
| 1 | 44200050 | WELDED WIRE REINF | 1,870 | SQ YD | $10.00 | $14.00 | $13.50 | $16.00 | |
| 2 | 44200970 | CL B PATCH T2 10 | 1,217 | SQ YD | $190.00 | $143.00 | $175.00 | $190.00 | |
| 3 | 44200974 | CL B PATCH T3 10 | 1,480 | SQ YD | $165.00 | $141.00 | $175.00 | $182.00 | |
| 4 | 44200976 | CL B PATCH T4 10 | 390 | SQ YD | $165.00 | $138.00 | $175.00 | $177.00 | |
| 5 | 44201299 | DOWEL BARS 1 1/2 | 4,860 | EACH | $8.50 | $21.00 | $30.00 | $27.00 | |
| 6 | 44213200 | SAW CUTS | 11,722 | FOOT | $0.0100 | $1.00 | $1.00 | $3.50 | |
| 7 | 44213204 | TIE BARS 3/4 | 957 | EACH | $3.50 | $13.00 | $24.50 | $15.00 | |
| 8 | 67100100 | MOBILIZATION | 1 | L SUM | $30,000.00 | $25,000.00 | $49,000.00 | $52,000.00 | |
| 9 | 70102625 | TR CONT & PROT 701606 | 1 | L SUM | $2,000.00 | $5,000.00 | $15,000.00 | $20,000.00 | |
| 10 | 70102630 | TR CONT & PROT 701601 | 1 | L SUM | $2,000.00 | $22,000.00 | $1,150.00 | $4,500.00 | |
| 11 | 70102635 | TR CONT & PROT 701701 | 1 | L SUM | $500.00 | $1,000.00 | $1,150.00 | $4,500.00 | |
| 12 | 70103815 | TR CONT SURVEILLANCE | 15 | CAL DA | $0.0100 | $10.00 | $545.00 | $180.00 | |
| 13 | 70106800 | CHANGEABLE MESSAGE SN | 4 | CAL MO | $0.0100 | $1,500.00 | $550.00 | $1,000.00 |