D2 PP 2019-2
- Let date
- Friday, June 14, 2019
- Contract
- 64N20 · job page
- District
- District 2
- County
- Rock Island
- Highway
- Limits
- Pavement patching on IL 5 and IL 5/IL 92 from Colona Road/Avenue of the Cities to the I-80/I-88 interchange.
Bidders 2
| # | Contractor | Total bid | vs estimate | vs low |
|---|---|---|---|---|
| EE | Engineer's estimate | — | ||
| 1 | G. M. Sipes Construction, Inc. Low bidder | $525,686 | ||
| 2 | Valley Construction Co. | $595,829 | +13.3% |
| Seq | Bid code | Description | Qty | Unit | Estimate | #1 G. M. Sipes Con… | #2 Valley Construc… |
|---|---|---|---|---|---|---|---|
| 1 | Z0048665 | RR PROT LIABILITY INS | 1 | L SUM | $5,000.00 | $5,500.00 | |
| 2 | 44200541 | CL A PATCH T2 9 | 580.6 | SQ YD | $175.00 | $190.00 | |
| 3 | 44200553 | CL A PATCH T2 10 | 238 | SQ YD | $180.00 | $206.00 | |
| 4 | 44200610 | CL A PATCH T2 13 | 334 | SQ YD | $190.00 | $240.00 | |
| 5 | 44201031 | CL B PATCH T2 15 | 548 | SQ YD | $200.00 | $275.00 | |
| 6 | 44201299 | DOWEL BARS 1 1/2 | 1,340 | EACH | $20.00 | $18.00 | |
| 7 | 44213000 | PATCH REINFORCEMENT | 1,152.6 | SQ YD | $50.00 | $68.00 | |
| 8 | 44213200 | SAW CUTS | 11,330 | FOOT | $6.95 | $2.50 | |
| 9 | 67100100 | MOBILIZATION | 1 | L SUM | $25,000.00 | $35,600.00 | |
| 10 | 70100310 | TRAF CONT-PROT 701421 | 1 | L SUM | $1.00 | $105.00 | |
| 11 | 70100320 | TRAF CONT-PROT 701422 | 1 | L SUM | $15,000.00 | $21,000.00 | |
| 12 | 70100420 | TRAF CONT-PROT 701411 | 6 | EACH | $1.00 | $525.00 | |
| 13 | 70103815 | TR CONT SURVEILLANCE | 15 | CAL DA | $0.0100 | $630.00 |