Bid tab 64N20

Let Jun 14, 2019 · District 2 · Rock Island Sign up free

‹ Jun 2019 results

D2 PP 2019-2

Let date
Friday, June 14, 2019
Contract
64N20 · job page
District
District 2
County
Rock Island
Highway
Limits
Pavement patching on IL 5 and IL 5/IL 92 from Colona Road/Avenue of the Cities to the I-80/I-88 interchange.

Bidders 2

#ContractorTotal bidvs estimatevs low
EEEngineer's estimate—
1 G. M. Sipes Construction, Inc. Low bidder $525,686
2 Valley Construction Co. $595,829 +13.3%

Bid tab: unit prices 13 items

ExcelCSV
SeqBid codeDescriptionQtyUnitEstimate #1 G. M. Sipes Con…#2 Valley Construc…
1Z0048665 RR PROT LIABILITY INS1L SUM $5,000.00 $5,500.00
244200541 CL A PATCH T2 9580.6SQ YD $175.00 $190.00
344200553 CL A PATCH T2 10238SQ YD $180.00 $206.00
444200610 CL A PATCH T2 13334SQ YD $190.00 $240.00
544201031 CL B PATCH T2 15548SQ YD $200.00 $275.00
644201299 DOWEL BARS 1 1/21,340EACH $20.00 $18.00
744213000 PATCH REINFORCEMENT1,152.6SQ YD $50.00 $68.00
844213200 SAW CUTS11,330FOOT $6.95 $2.50
967100100 MOBILIZATION1L SUM $25,000.00 $35,600.00
1070100310 TRAF CONT-PROT 7014211L SUM $1.00 $105.00
1170100320 TRAF CONT-PROT 7014221L SUM $15,000.00 $21,000.00
1270100420 TRAF CONT-PROT 7014116EACH $1.00 $525.00
1370103815 TR CONT SURVEILLANCE15CAL DA $0.0100 $630.00